| SECTION 6.0 | COMPARISON OF ALTERNATIVES |
6.1 INTRODUCTION
This section provides a summary comparison of potentially significant impacts for the proposed Project and Project Alternatives, including ancillary facilities. Refer to Section 4.0 (Proposed Project) and Section 5.0 (Project Alternatives) of the Draft EIR as well as Sections 1.0 and 4.A of this Final EIR for more information regarding specific impacts and proposed mitigation measures. The "No Project Alternative" is also included for comparison purposes. Refer to Section A.8.3 in Appendix A of the Draft EIR and Sections 1.0 and 3.0 of this Final EIR for a discussion of alternatives that were considered but eliminated from further consideration, including the rationale for elimination. This section is intended to replace Section 6.0 provided in the Draft EIR.
As discussed previously in Sections 1.0, 3.0, and 4.A of this Final EIR, the proposed Trans Bay Cable Project now consists of the proposed San Francisco HWC (Mitigated) Converter Station site, the proposed Pittsburg West Tenth Street Alternative 1 (E/W) Converter Station site, onshore AC cables, and the proposed HVDC submarine cable. The previously proposed San Francisco HWC site layout and the Pittsburg Standard Oil Converter Station site, including ancillary facilities as evaluated in the Draft EIR, have been eliminated from further consideration in the Final EIR. The comparison of alternatives presented herein reflects these Project refinements.
The proposed Project and Project Alternatives considered in this comparison of potentially significant impacts are as follows:
6.2 COMPARISON OF ALTERNATIVES
The potentially significant impact findings (including potential impacts, proposed mitigation measures, and residual impact findings) for the proposed and alternative Project components are summarized in Table 6-1.
As shown in Table 6-1, the identified potentially significant impacts, mitigation measures, and residual impact findings for the proposed and alternative converter station sites (including ancillary facilities) in San Francisco and Pittsburg are very similar, except as noted in Section 6.3. The identified potentially significant impacts associated with the submarine cable installation in the Bay are essentially the same for all converter station sites.
6.2.1 San Francisco Converter Stations
6.2.2 Pittsburg Converter Stations
6.2.3 No Project Alternative
As shown in Table 6-1, the No Project Alternative would avoid the potential environmental impacts of the proposed Trans Bay Cable Project, including those associated with the identified Project Alternatives.
The No Project Alternative would involve taking no action to provide additional electrical transmission capacity to San Francisco (i.e., status quo). Under the No Project Alternative, the potential environmental impacts and benefits of the proposed Trans Bay Cable Project would not occur as a direct consequence of Project implementation. However, the No Project Alternative is incapable of meeting the Project goals and objectives, or the CAISO's objectives for solving the near-term and long-term electrical supply and reliability issues in San Francisco and the northern Peninsula area. Another potential consequence of the No Project Alternative would be the lost potential to save an estimated 20 MW of electrical power that is currently expended in line losses, which would be avoided by the proposed Project. In summary, the No Project Alternative does not constitute a reasonable alternative to the proposed HVDC Project.
6.3 ENVIRONMENTALLY SUPERIOR ALTERNATIVE
The No Project Alternative would result in the fewest environmental effects. However, the No Project Alternative would not meet the Project/CAISO goals and is not considered to be a reasonable or feasible alternative. Numerous "non-Project" alternatives were also considered, as discussed in Section A.8.3 in Appendix A of the Draft EIR. None of the various alternatives evaluated are considered to be capable of meeting all of the Project objectives and the related screening criteria for "feasibility" and "environmental impacts avoidance and minimization." Therefore, none of the potential non-Project alternatives were retained for further consideration in this EIR.
The Trans Bay Cable Project Alternatives are considered by the City of Pittsburg to be the only feasible alternative for meeting the Project and CAISO objectives at this point in time.
It is difficult to determine, however, which of the Trans Bay Cable Project converter station site alternatives in San Francisco and Pittsburg is clearly the environmentally superior alternative as, with few exceptions, the sites are very similar to each other in terms of potential impacts. The proposed San Francisco HWC (Mitigated) Converter Station site and the San Francisco Sheedy Converter Station Alternative would avoid the unavoidable adverse significant impact to historic architectural resources associated with the alternative San Francisco Mirant sites. However, Mirant tentatively plans to demolish the buildings considered to be historic (i.e., Station A Complex) on the San Francisco Mirant property due to their deteriorated condition and seismic safety concerns. Locating the proposed Trans Bay Cable Project San Francisco converter station on any one of the three alternative Mirant site layouts would consolidate the electrical station facilities (i.e., PG&E Potrero Substation and the Trans Bay Cable San Francisco converter station) at one location and would avoid potential conflicts with possible future improvements to public access to San Francisco Bay (Impact LU-1) associated with the Sheedy alternative. In addition, the required electrical interconnection (115 kV AC) between the Sheedy Converter Station site and the PG&E Potrero Substation is problematic due to potential conflicts with existing underground utilities along Illinois Street. No one site in San Francisco is clearly environmentally superior to another. The proposed HWC (Mitigated) site has no identified unavoidable adverse significant impacts and this is the only site in San Francisco for which the Project proponent has site control, thus the HWC (Mitigated) site is the only feasible site at the time this Final EIR was prepared.
Of the proposed and alternative converter station sites in Pittsburg (including ancillary facilities), it is also difficult to determine the clearly environmentally superior alternative. Due to the unavoidable adverse significant noise and visual impacts associated with the Pittsburg West Tenth Street Alternative 2 site, this alternative site is the least preferable from an environmental impact perspective. Accordingly, the proposed Pittsburg West Tenth Street Alternative 1 (E/W) and Pittsburg Mirant alternative sites are considered to be environmentally superior to the Pittsburg West Tenth Street Alternative 2 site. It is not possible to clearly differentiate the environmentally superior alternative in Pittsburg between the West Tenth Street Alternative 1 site and the Pittsburg Mirant site. However, since the Project proponent does not have site control at the Pittsburg Mirant site, the Pittsburg West Tenth Street Alternative 1 (E/W) site is the only environmentally acceptable and feasible site at the time this Final EIR was prepared.
|
Impact |
Mitigation Measure |
Proposed San Francisco HWC (Mitigated) Converter Station |
Proposed Pittsburg
West Tenth Street Alternative 1 |
Proposed Offshore DC Cable Route |
San Francisco Mirant Converter Station Alternative |
San Francisco Sheedy Converter Station Alternative |
Pittsburg West Tenth Street Converter Station (Alternative 2) |
Pittsburg Mirant Converter Station Alternative |
No Project Alternative |
|
Air Quality |
|||||||||
|
AIR-1: Fugitive Dust Emissions |
|||||||||
|
|
AIR-1: Fugitive Dust Controls |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
AIR-2: Equipment Exhaust Emissions |
|||||||||
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
AIR-3: Marine Construction – Criteria Pollutants |
|||||||||
|
|
AIR-3: Marine Vessel Emission Controls |
|
|
X |
|
|
|
|
|
|
|
Resulting Level of Significance |
|
|
LTS |
|
|
|
|
|
|
AIR-4: Marine Construction – Toxic Air Contaminants |
|||||||||
|
|
AIR-4: Implement Mitigation Measure AIR-3 |
|
|
X |
|
|
|
|
|
|
|
Resulting Level of Significance |
|
|
LTS |
|
|
|
|
|
|
Geologic Resources and Soils |
|||||||||
|
GEO-1: Soil Erosion and Compaction |
|||||||||
|
|
GEO-1: Design Project for Erosion Control |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
GEO-2: Asbestos-containing Serpentine |
|||||||||
|
|
GEO-2: Controls for Excavation of Serpentine |
X |
|
|
X |
X |
|
|
|
|
|
Resulting Level of Significance |
LTS |
|
|
LTS |
LTS |
|
|
|
|
GEO-3: Strong Ground Shaking |
|||||||||
|
|
GEO-3: Design to Seismic Design Requirements |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
GEO-4: Liquefaction |
|||||||||
|
|
GEO-4: Design Project for Liquefiable Deposits |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
GEO-5: Shrink-Swell/Subsidence |
|||||||||
|
|
GEO-5: Design Project for Shrink-Swell/Subsidence |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
Water Resources and Quality |
|||||||||
|
WATER-1: Erosion and Contaminated Runoff |
|||||||||
|
|
WATER-1: Erosion Control and Contaminant Source Control |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
WATER-2: Surface Water Quality Impacts from HDD |
|||||||||
|
|
WATER-2: Spill Prevention and Control Plan for HDD |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
WATER-3: Groundwater Quality Impacts from HDD |
|||||||||
|
|
WATER-3: Use of Pilot Hole and Reaming |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
WATER-5. Water Quality Impacts from Cable Laying Operation |
|||||||||
|
|
WATER-5: Avoidance of Sediment Contamination |
|
|
X |
|
|
|
|
|
|
|
Resulting Level of Significance |
|
|
LTS |
|
|
|
|
|
|
WATER-7: Water Quality Impacts from Vessel Fuel Spills |
|||||||||
|
|
WATER-7: Vessel Fuel Spill Response Plan |
|
|
X |
|
|
|
|
|
|
|
Resulting Level of Significance |
|
|
LTS |
|
|
|
|
|
|
WATER-8: Flooding |
|||||||||
|
|
WATER-8: Flood Mitigation |
|
X |
|
|
|
|
X |
|
|
|
Resulting Level of Significance |
|
LTS |
|
|
|
|
LTS |
|
|
Terrestrial Biological Resources |
|||||||||
|
TBIO-3: Disturbance or Fill of Wetlands and Streams |
|||||||||
|
|
TBIO-3e: Implement HDD or Comparable Technology Techniques to Avoid Impacts to Wetlands |
|
|
|
|
|
X |
|
|
|
|
Resulting Level of Significance |
|
|
|
|
|
LTS |
|
|
|
TBIO-4: Potential Impacts to Giant Garter Snake and Western Pond Turtle |
|||||||||
|
|
TBIO-4a: Avoidance of Habitat and Timing of Construction |
|
|
|
|
|
X |
|
|
|
|
TBIO-4b: Worker Training for Giant Garter Snake and Western Pond Turtle |
|
|
|
|
|
X |
|
|
|
|
TBIO-4c: Biological Monitoring for Giant Garter Snake and Western Pond Turtle |
|
|
|
|
|
X |
|
|
|
|
TBIO-4d: Avoiding Impacts to Wetlands and Habitat |
|
|
|
|
|
X |
|
|
|
|
Resulting Level of Significance |
|
|
|
|
|
LTS |
|
|
|
Marine Biological Resources |
|||||||||
|
No potentially significant impacts |
|||||||||
|
Cultural Resources |
|||||||||
|
CUL-1: Disturbance of Archaeological Resources |
|||||||||
|
|
CUL-1a: Archeological Resource Testing |
X |
|
|
X |
|
|
|
|
|
|
CUL-1b: Archaeological Resource Data Recovery |
X |
|
|
X |
|
|
|
|
|
|
CUL-1c: Archaeological Resource Construction Monitoring |
X |
|
|
X |
|
|
|
|
|
|
Resulting Level of Significance |
LTS |
|
|
LTS |
|
|
|
|
|
CUL-2: Demolition of Historic Architectural Resources |
|||||||||
|
|
CUL-2a: Recording Architectural Resources |
|
|
|
X |
|
|
|
|
|
|
CUL-2b: Architectural Resource Interpretive Display and/or Interpretive Material |
|
|
|
X |
|
|
|
|
|
|
CUL-2c: Architectural Resource Salvage Opportunities |
|
|
|
X |
|
|
|
|
|
|
CUL-2d: Coordination with Central Waterfront Historic Preservation |
|
|
|
X |
|
|
|
|
|
|
Resulting Level of Significance |
|
|
|
RS |
|
|
|
|
|
CUL-3: Offshore Cable Route Archaeological Resources |
|||||||||
|
|
CUL-3a: Archaeological Resources Geophysical Survey |
|
|
X |
|
|
|
|
|
|
|
CUL-3b: Archaeological Resources Avoidance |
|
|
X |
|
|
|
|
|
|
|
CUL-3c: Archaeological Resources Supplemental Underwater Investigation |
|
|
X |
|
|
|
|
|
|
|
Resulting Level of Significance |
|
|
LTS |
|
|
|
|
|
|
Land Use and Recreation |
|||||||||
|
LU-1: Potential Conflict with Public Access Improvements |
|||||||||
|
|
LU-1: Public Access |
|
|
|
|
X |
|
|
|
|
|
Resulting Level of Significance |
|
|
|
|
LTS |
|
|
|
|
LU-4: Increased Vessel Traffic |
|||||||||
|
|
LU-4a: Vessel Crew Procedures |
|
|
X |
|
|
|
|
|
|
|
LU-4b: Coast Guard Coordination |
|
|
X |
|
|
|
|
|
|
|
Resulting Level of Significance |
|
|
LTS |
|
|
|
|
|
|
LU-5: Potential Conflict with Local Plans and Policies |
|||||||||
|
|
LU-5: Local Plans and Policies Coordination |
|
|
X |
|
|
|
|
|
|
|
Resulting Level of Significance |
|
|
LTS |
|
|
|
|
|
|
Commercial Fishing and Marine Transportation |
|||||||||
|
MTRANS-1: Vessel Navigation Hazards |
|||||||||
|
|
MTRANS-1a: Project Registration, Information and Pilotage |
|
|
X |
|
|
|
|
|
|
|
MTRANS-1b: Compliance with Navigation Rules |
|
|
X |
|
|
|
|
|
|
|
MTRANS-1c: Precautionary Area |
|
|
X |
|
|
|
|
|
|
|
MTRANS-1d: Publication of Cable Location |
|
|
X |
|
|
|
|
|
|
|
Resulting Level of Significance |
|
|
LTS |
|
|
|
|
|
|
MTRANS-2: Interference with Commercial Fishing Operations |
|||||||||
|
|
MTRANS-2a: Commercial Fishing Avoidance |
|
|
X |
|
|
|
|
|
|
|
MTRANS-2b: Project Information |
|
|
X |
|
|
|
|
|
|
|
Resulting Level of Significance |
|
|
LTS |
|
|
|
|
|
|
MTRANS-3: Interference with Commercial Sport Fishing Operations |
|||||||||
|
|
MTRANS-3a: Commercial Sport Fishing Avoidance |
|
|
X |
|
|
|
|
|
|
|
MTRANS-3b: Project Information |
|
|
X |
|
|
|
|
|
|
|
Resulting Level of Significance |
|
|
LTS |
|
|
|
|
|
|
Traffic and Transportation |
|||||||||
|
TRAFFIC-1: Cumulative Traffic Impacts |
|||||||||
|
|
TRAFFIC-1: Coordination to Reduce Cumulative Traffic Impacts |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
TRAFFIC-2: Oversized Loads |
|||||||||
|
|
TRAFFIC-2: Coordination of Oversized Loads |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
TRAFFIC-3: Temporary Street Closures Affecting Traffic, Bicycle, and Pedestrian Circulation |
|||||||||
|
|
TRAFFIC-3: Signage for Temporary Street Closures |
X |
|
|
X |
X |
|
|
|
|
|
Resulting Level of Significance |
LTS |
|
|
LTS |
LTS |
|
|
|
|
TRAFFIC-4: Impacts on Metro East Light Rail Facility |
|||||||||
|
|
TRAFFIC-4: Reducing Impact on the Movement of MUNI Light Rail Vehicles into and out of the Metro East Maintenance Facility |
X |
|
|
X |
X |
|
|
|
|
|
Resulting Level of Significance |
LTS |
|
|
LTS |
LTS |
|
|
|
|
Noise and Vibration |
|||||||||
|
NOISE-1: Converter Station Operations Sound Levels |
|||||||||
|
|
NOISE-1: Noise Barrier Installation for Converter Station |
|
X |
|
|
|
X |
X |
|
|
|
Resulting Level of Significance |
|
LTS |
|
|
|
LTS |
LTS |
|
|
NOISE-2: Construction Sound Level |
|||||||||
|
|
NOISE-2: Construction Noise Control Measures |
|
|
|
|
|
X |
|
|
|
|
Resulting Level of Significance |
|
|
|
|
|
RS |
|
|
|
Public Services and Utilities |
|||||||||
|
PS-1: Construction Fire Hazards |
|||||||||
|
|
PS-1: Construction Fire Prevention |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
PS-2: Existing Onshore Underground Utilities |
|||||||||
|
|
PS-2: Utility Survey |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
PS-3: Operations Fire Hazards |
|||||||||
|
|
PS-3: Operations Fire Prevention |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
PS-4: Water Service |
|||||||||
|
|
PS-4: Water Service |
|
|
|
|
|
|
X |
|
|
|
Resulting Level of Significance |
|
|
|
|
|
|
LTS |
|
|
Visual Resources |
|||||||||
|
VIS-1: Converter Station Domination of View |
|||||||||
|
|
VIS-1a: Plan Submittal Requirements for Building Materials and Colors |
X |
X |
|
|
X |
|
X |
|
|
|
VIS-1b: Plan Submittal Requirements for Landscaping |
X |
X |
|
|
X |
|
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
|
LTS |
|
LTS |
|
|
VIS-2: Converter Station Will Create Substantial Light and Glare |
|||||||||
|
|
VIS-2: Plan Submittal Requirements for Lighting |
X |
X |
|
X |
X |
X |
|
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
|
|
|
VIS-3: Creation of Visual Clutter |
|||||||||
|
|
VIS-3: Landscaping Plan |
X |
|
|
|
|
|
|
|
|
|
Resulting Level of Significance |
LTS |
|
|
|
|
|
|
|
|
VIS-4: Converter Station Domination of Entrance to Warm Water Cove Park |
|||||||||
|
|
VIS-4a: Landscaping |
|
|
|
|
X |
|
|
|
|
|
VIS-4b: Common Fence Design |
|
|
|
|
X |
|
|
|
|
|
VIS-4c: Street Lighting along 24th Street |
|
|
|
|
X |
|
|
|
|
|
Resulting Level of Significance |
|
|
|
|
LTS |
|
|
|
|
VIS-5: Converter Station Domination of View |
|||||||||
|
|
VIS-5a: Street Yard Setback |
|
|
|
|
|
X |
|
|
|
|
VIS-5b: Street Yard Landscape |
|
|
|
|
|
X |
|
|
|
|
VIS-5c: Architectural Design and Building Colors |
|
|
|
|
|
X |
|
|
|
|
Resulting Level of Significance |
|
|
|
|
|
RS |
|
|
|
Hazardous Materials and Waste Management |
|||||||||
|
HAZ-1: Removal of Potentially Hazardous Building Materials Resulting from Demolition |
|||||||||
|
|
HAZ-1: Complete an ACM Abatement Plan and an LBP Abatement Plan |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
HAZ-2: Soil Removal |
|||||||||
|
|
HAZ-2: Soil Removal Protocols |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
HAZ-3: Construction-phase Hazardous Materials Use |
|||||||||
|
|
HAZ-3: Reduction of Hazards During Construction Phase |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
HAZ-4: Construction-phase Waste Streams |
|||||||||
|
|
HAZ-4: Management of Construction-phase Waste Streams |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
HAZ-5: Construction-phase Accidental Spills |
|||||||||
|
|
HAZ-5: Construction-phase Spill Prevention, Control, and Countermeasure |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
HAZ-6: Construction-phase Dust and Volatilization of Contaminants |
|||||||||
|
|
HAZ-6: Reduction of Construction Dust and Volatilization of Contaminants |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
HAZ-7: Contaminated Groundwater |
|||||||||
|
|
HAZ-7: Contaminated Groundwater Control |
X |
|
|
X |
X |
|
|
|
|
|
Resulting Level of Significance |
LTS |
|
|
LTS |
LTS |
|
|
|
|
HAZ-8: Operations-phase Hazardous Materials Usage |
|||||||||
|
|
HAZ-8: Control of Operations-phase Hazardous Materials |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
HAZ-9: Operations-phase Waste Streams |
|||||||||
|
|
HAZ-9: Manage Waste Generation, Storage and Disposal During Operations Phase |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
HAZ-10: Operations-phase Accidental Spills |
|||||||||
|
|
HAZ-10: Operations-phase Spill Prevention, Control, and Countermeasure |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
HAZ-11: Operations-phase Fire and Explosion Risk |
|||||||||
|
|
HAZ-11: Reduction of Fire and Explosion Risk and Emergency Support During Operations Phase |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
HAZ-12: Impacts from Seismic Activity |
|||||||||
|
|
HAZ-12: Manage Seismic Activity |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
|
Paleontological Resources |
|||||||||
|
PALEO-1: Disturbance of Fossil Resources |
|||||||||
|
|
PALEO-1: Potential Fossil Resources Protection |
X |
X |
|
X |
X |
X |
X |
|
|
|
Resulting Level of Significance |
LTS |
LTS |
|
LTS |
LTS |
LTS |
LTS |
|
1 X = Applicable; Blank = Not Applicable; LTS = Less
than Significant; RS = Residual Significant Impact.
2 Note: The impacts and
mitigation measures presented in this table reflect mitigating refinements made
to the Project between the Draft and Final EIRs.
| Return to the Table of Contents. | Open the Draft EIR in a new window. | On to the next section. |