SECTION 6.0 COMPARISON OF ALTERNATIVES

6.1    INTRODUCTION

This section provides a summary comparison of potentially significant impacts for the proposed Project and Project Alternatives, including ancillary facilities. Refer to Section 4.0 (Proposed Project) and Section 5.0 (Project Alternatives) of the Draft EIR as well as Sections 1.0 and 4.A of this Final EIR for more information regarding specific impacts and proposed mitigation measures. The "No Project Alternative" is also included for comparison purposes. Refer to Section A.8.3 in Appendix A of the Draft EIR and Sections 1.0 and 3.0 of this Final EIR for a discussion of alternatives that were considered but eliminated from further consideration, including the rationale for elimination. This section is intended to replace Section 6.0 provided in the Draft EIR.

As discussed previously in Sections 1.0, 3.0, and 4.A of this Final EIR, the proposed Trans Bay Cable Project now consists of the proposed San Francisco HWC (Mitigated) Converter Station site, the proposed Pittsburg West Tenth Street Alternative 1 (E/W) Converter Station site, onshore AC cables, and the proposed HVDC submarine cable. The previously proposed San Francisco HWC site layout and the Pittsburg Standard Oil Converter Station site, including ancillary facilities as evaluated in the Draft EIR, have been eliminated from further consideration in the Final EIR. The comparison of alternatives presented herein reflects these Project refinements.

The proposed Project and Project Alternatives considered in this comparison of potentially significant impacts are as follows:

  • Proposed San Francisco HWC (Mitigated) Converter Station

  • Proposed Pittsburg West Tenth Street Converter Station (Alternative 1 [E/W])

  • Proposed Offshore DC Cable Route

  • San Francisco Mirant Converter Station Alternative (three site layouts)

  • San Francisco Sheedy Converter Station Alternative

  • Pittsburg West Tenth Street Converter Station (Alternative 2 [N/S])

  • Pittsburg Mirant Converter Station Alternative

  • No Project Alternative

6.2    COMPARISON OF ALTERNATIVES

The potentially significant impact findings (including potential impacts, proposed mitigation measures, and residual impact findings) for the proposed and alternative Project components are summarized in Table 6-1.

As shown in Table 6-1, the identified potentially significant impacts, mitigation measures, and residual impact findings for the proposed and alternative converter station sites (including ancillary facilities) in San Francisco and Pittsburg are very similar, except as noted in Section 6.3. The identified potentially significant impacts associated with the submarine cable installation in the Bay are essentially the same for all converter station sites.

6.2.1    San Francisco Converter Stations

  • The alternative San Francisco Mirant Converter Station (three layouts) site(s) would result in unavoidable adverse significant impacts associated with the required demolition of historic architectural resources (Impact CUL-2), whereas the proposed San Francisco HWC (Mitigated) Converter Station and alternative San Francisco Sheedy Converter Station would not.

  • The alternative San Francisco Sheedy Converter Station would involve a potentially significant impact associated with potential conflicts with possible future improvements to public access to San Francisco Bay (Impact LU-1), whereas the proposed San Francisco HWC (Mitigated) Converter Station and alternative San Francisco Mirant Converter Station (three site layouts) would not; with implementation of Mitigation Measure LU-1, this potentially significant impact would be reduced to a less-than-significant level.

  • Potential environmental impacts associated with the offshore submarine HVDC cable for the proposed HWC (Mitigated) and alternative Mirant and Sheedy converter station sites are the same and, with implementation of mitigation measures, all identified potentially significant impacts would be reduced to less-than-significant levels.

6.2.2    Pittsburg Converter Stations

  • The proposed Pittsburg West Tenth Street Alternative 1 (E/W) Converter Station as well as the Pittsburg Mirant site would not result in any unavoidable adverse significant environmental impacts, whereas the Pittsburg West Tenth Street Alternative 2 would result in unavoidable significant adverse construction/pile driving noise (Impact
    NOISE-2) and long-term visual impacts (Impact VIS-5).

  • The northwest portion of the proposed Pittsburg West Tenth Street Alternative 1 (E/W) site and the entire Pittsburg Mirant site are within the 100-year flood zone (Impact WATER-8) while the Pittsburg West Tenth Street Alternative 2 (N/S) site is not.

6.2.3    No Project Alternative

As shown in Table 6-1, the No Project Alternative would avoid the potential environmental impacts of the proposed Trans Bay Cable Project, including those associated with the identified Project Alternatives.

The No Project Alternative would involve taking no action to provide additional electrical transmission capacity to San Francisco (i.e., status quo). Under the No Project Alternative, the potential environmental impacts and benefits of the proposed Trans Bay Cable Project would not occur as a direct consequence of Project implementation. However, the No Project Alternative is incapable of meeting the Project goals and objectives, or the CAISO's objectives for solving the near-term and long-term electrical supply and reliability issues in San Francisco and the northern Peninsula area. Another potential consequence of the No Project Alternative would be the lost potential to save an estimated 20 MW of electrical power that is currently expended in line losses, which would be avoided by the proposed Project. In summary, the No Project Alternative does not constitute a reasonable alternative to the proposed HVDC Project.

6.3    ENVIRONMENTALLY SUPERIOR ALTERNATIVE

The No Project Alternative would result in the fewest environmental effects. However, the No Project Alternative would not meet the Project/CAISO goals and is not considered to be a reasonable or feasible alternative. Numerous "non-Project" alternatives were also considered, as discussed in Section A.8.3 in Appendix A of the Draft EIR. None of the various alternatives evaluated are considered to be capable of meeting all of the Project objectives and the related screening criteria for "feasibility" and "environmental impacts avoidance and minimization." Therefore, none of the potential non-Project alternatives were retained for further consideration in this EIR.

The Trans Bay Cable Project Alternatives are considered by the City of Pittsburg to be the only feasible alternative for meeting the Project and CAISO objectives at this point in time.

It is difficult to determine, however, which of the Trans Bay Cable Project converter station site alternatives in San Francisco and Pittsburg is clearly the environmentally superior alternative as, with few exceptions, the sites are very similar to each other in terms of potential impacts. The proposed San Francisco HWC (Mitigated) Converter Station site and the San Francisco Sheedy Converter Station Alternative would avoid the unavoidable adverse significant impact to historic architectural resources associated with the alternative San Francisco Mirant sites. However, Mirant tentatively plans to demolish the buildings considered to be historic (i.e., Station A Complex) on the San Francisco Mirant property due to their deteriorated condition and seismic safety concerns. Locating the proposed Trans Bay Cable Project San Francisco converter station on any one of the three alternative Mirant site layouts would consolidate the electrical station facilities (i.e., PG&E Potrero Substation and the Trans Bay Cable San Francisco converter station) at one location and would avoid potential conflicts with possible future improvements to public access to San Francisco Bay (Impact LU-1) associated with the Sheedy alternative. In addition, the required electrical interconnection (115 kV AC) between the Sheedy Converter Station site and the PG&E Potrero Substation is problematic due to potential conflicts with existing underground utilities along Illinois Street. No one site in San Francisco is clearly environmentally superior to another. The proposed HWC (Mitigated) site has no identified unavoidable adverse significant impacts and this is the only site in San Francisco for which the Project proponent has site control, thus the HWC (Mitigated) site is the only feasible site at the time this Final EIR was prepared.

Of the proposed and alternative converter station sites in Pittsburg (including ancillary facilities), it is also difficult to determine the clearly environmentally superior alternative. Due to the unavoidable adverse significant noise and visual impacts associated with the Pittsburg West Tenth Street Alternative 2 site, this alternative site is the least preferable from an environmental impact perspective. Accordingly, the proposed Pittsburg West Tenth Street Alternative 1 (E/W) and Pittsburg Mirant alternative sites are considered to be environmentally superior to the Pittsburg West Tenth Street Alternative 2 site. It is not possible to clearly differentiate the environmentally superior alternative in Pittsburg between the West Tenth Street Alternative 1 site and the Pittsburg Mirant site. However, since the Project proponent does not have site control at the Pittsburg Mirant site, the Pittsburg West Tenth Street Alternative 1 (E/W) site is the only environmentally acceptable and feasible site at the time this Final EIR was prepared.

 


TABLE 6-11, 2
SUMMARY OF POTENTIALLY SIGNIFICANT IMPACTS AND MITIGATION MEASURES


Impact

Mitigation Measure

Proposed San Francisco HWC (Mitigated) Converter Station

Proposed Pittsburg West Tenth Street Alternative 1
Converter Station

Proposed Offshore DC Cable Route

San Francisco Mirant Converter Station Alternative

San Francisco Sheedy Converter Station Alternative

Pittsburg West Tenth Street Converter Station (Alternative 2)

Pittsburg Mirant Converter Station Alternative

No Project Alternative

Air Quality

AIR-1: Fugitive Dust Emissions

 

AIR-1: Fugitive Dust Controls

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

AIR-2: Equipment Exhaust Emissions

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

AIR-3: Marine Construction – Criteria Pollutants

 

AIR-3: Marine Vessel Emission Controls

 

 

X

 

 

 

 

 

 

Resulting Level of Significance

 

 

LTS

 

 

 

 

 

AIR-4: Marine Construction – Toxic Air Contaminants

 

AIR-4: Implement Mitigation Measure AIR-3

 

 

X

 

 

 

 

 

 

Resulting Level of Significance

 

 

LTS

 

 

 

 

 

Geologic Resources and Soils

GEO-1: Soil Erosion and Compaction

 

GEO-1: Design Project for Erosion Control

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

GEO-2: Asbestos-containing Serpentine

 

GEO-2: Controls for Excavation of Serpentine

X

 

 

X

X

 

 

 

 

Resulting Level of Significance

LTS

 

 

LTS

LTS

 

 

 

GEO-3: Strong Ground Shaking

 

GEO-3: Design to Seismic Design Requirements

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

GEO-4: Liquefaction

 

GEO-4: Design Project for Liquefiable Deposits

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

GEO-5: Shrink-Swell/Subsidence

 

GEO-5: Design Project for Shrink-Swell/Subsidence

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

Water Resources and Quality

WATER-1: Erosion and Contaminated Runoff

 

WATER-1: Erosion Control and Contaminant Source Control

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

WATER-2: Surface Water Quality Impacts from HDD

 

WATER-2: Spill Prevention and Control Plan for HDD

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

WATER-3: Groundwater Quality Impacts from HDD

 

WATER-3: Use of Pilot Hole and Reaming

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

WATER-5. Water Quality Impacts from Cable Laying Operation

 

WATER-5: Avoidance of Sediment Contamination

 

 

X

 

 

 

 

 

 

Resulting Level of Significance

 

 

LTS

 

 

 

 

 

WATER-7: Water Quality Impacts from Vessel Fuel Spills

 

WATER-7: Vessel Fuel Spill Response Plan

 

 

X

 

 

 

 

 

 

Resulting Level of Significance

 

 

LTS

 

 

 

 

 

WATER-8: Flooding

 

WATER-8: Flood Mitigation

 

X

 

 

 

 

X

 

 

Resulting Level of Significance

 

LTS

 

 

 

 

LTS

 

Terrestrial Biological Resources

TBIO-3: Disturbance or Fill of Wetlands and Streams

 

TBIO-3e: Implement HDD or Comparable Technology Techniques to Avoid Impacts to Wetlands

 

 

 

 

 

X

 

 

 

Resulting Level of Significance

 

 

 

 

 

LTS

 

 

TBIO-4: Potential Impacts to Giant Garter Snake and Western Pond Turtle

 

TBIO-4a: Avoidance of Habitat and Timing of Construction

 

 

 

 

 

X

 

 

 

TBIO-4b: Worker Training for Giant Garter Snake and Western Pond Turtle

 

 

 

 

 

X

 

 

 

TBIO-4c: Biological Monitoring for Giant Garter Snake and Western Pond Turtle

 

 

 

 

 

X

 

 

 

TBIO-4d: Avoiding Impacts to Wetlands and Habitat

 

 

 

 

 

X

 

 

 

Resulting Level of Significance

 

 

 

 

 

LTS

 

 

Marine Biological Resources

No potentially significant impacts

Cultural Resources

CUL-1: Disturbance of Archaeological Resources

 

CUL-1a: Archeological Resource Testing

X

 

 

X

 

 

 

 

 

CUL-1b: Archaeological Resource Data Recovery

X

 

 

X

 

 

 

 

 

CUL-1c: Archaeological Resource Construction Monitoring

X

 

 

X

 

 

 

 

 

Resulting Level of Significance

LTS

 

 

LTS

 

 

 

 

CUL-2: Demolition of Historic Architectural Resources

 

CUL-2a: Recording Architectural Resources

 

 

 

X

 

 

 

 

 

CUL-2b: Architectural Resource Interpretive Display and/or Interpretive Material

 

 

 

X

 

 

 

 

 

CUL-2c: Architectural Resource Salvage Opportunities

 

 

 

X

 

 

 

 

 

CUL-2d: Coordination with Central Waterfront Historic Preservation

 

 

 

X

 

 

 

 

 

Resulting Level of Significance

 

 

 

RS

 

 

 

 

CUL-3: Offshore Cable Route Archaeological Resources

 

CUL-3a: Archaeological Resources Geophysical Survey

 

 

X

 

 

 

 

 

 

CUL-3b: Archaeological Resources Avoidance

 

 

X

 

 

 

 

 

 

CUL-3c: Archaeological Resources Supplemental Underwater Investigation

 

 

X

 

 

 

 

 

 

Resulting Level of Significance

 

 

LTS

 

 

 

 

 

Land Use and Recreation

LU-1: Potential Conflict with Public Access Improvements

 

LU-1: Public Access

 

 

 

 

X

 

 

 

 

Resulting Level of Significance

 

 

 

 

LTS

 

 

 

LU-4: Increased Vessel Traffic

 

LU-4a: Vessel Crew Procedures

 

 

X

 

 

 

 

 

 

LU-4b: Coast Guard Coordination

 

 

X

 

 

 

 

 

 

Resulting Level of Significance

 

 

LTS

 

 

 

 

 

LU-5: Potential Conflict with Local Plans and Policies

 

LU-5: Local Plans and Policies Coordination

 

 

X

 

 

 

 

 

 

Resulting Level of Significance

 

 

LTS

 

 

 

 

 

Commercial Fishing and Marine Transportation

MTRANS-1: Vessel Navigation Hazards

 

MTRANS-1a: Project Registration, Information and Pilotage

 

 

X

 

 

 

 

 

 

MTRANS-1b: Compliance with Navigation Rules

 

 

X

 

 

 

 

 

 

MTRANS-1c: Precautionary Area

 

 

X

 

 

 

 

 

 

MTRANS-1d: Publication of Cable Location

 

 

X

 

 

 

 

 

 

Resulting Level of Significance

 

 

LTS

 

 

 

 

 

MTRANS-2: Interference with Commercial Fishing Operations

 

MTRANS-2a: Commercial Fishing Avoidance

 

 

X

 

 

 

 

 

 

MTRANS-2b: Project Information

 

 

X

 

 

 

 

 

 

Resulting Level of Significance

 

 

LTS

 

 

 

 

 

MTRANS-3: Interference with Commercial Sport Fishing Operations

 

MTRANS-3a: Commercial Sport Fishing Avoidance

 

 

X

 

 

 

 

 

 

MTRANS-3b: Project Information

 

 

X

 

 

 

 

 

 

Resulting Level of Significance

 

 

LTS

 

 

 

 

 

Traffic and Transportation

TRAFFIC-1: Cumulative Traffic Impacts

 

TRAFFIC-1: Coordination to Reduce Cumulative Traffic Impacts

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

TRAFFIC-2: Oversized Loads

 

TRAFFIC-2: Coordination of Oversized Loads

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

TRAFFIC-3: Temporary Street Closures Affecting Traffic, Bicycle, and Pedestrian Circulation

 

TRAFFIC-3: Signage for Temporary Street Closures

X

 

 

X

X

 

 

 

 

Resulting Level of Significance

LTS

 

 

LTS

LTS

 

 

 

TRAFFIC-4: Impacts on Metro East Light Rail Facility

 

TRAFFIC-4: Reducing Impact on the Movement of MUNI Light Rail Vehicles into and out of the Metro East Maintenance Facility

X

 

 

X

X

 

 

 

 

Resulting Level of Significance

LTS

 

 

LTS

LTS

 

 

 

Noise and Vibration

NOISE-1: Converter Station Operations Sound Levels

 

NOISE-1: Noise Barrier Installation for Converter Station

 

X

 

 

 

X

X

 

 

Resulting Level of Significance

 

LTS

 

 

 

LTS

LTS

 

NOISE-2: Construction Sound Level

 

NOISE-2: Construction Noise Control Measures

 

 

 

 

 

X

 

 

 

Resulting Level of Significance

 

 

 

 

 

RS

 

 

Public Services and Utilities

PS-1: Construction Fire Hazards

 

PS-1: Construction Fire Prevention

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

PS-2: Existing Onshore Underground Utilities

 

PS-2: Utility Survey

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

PS-3: Operations Fire Hazards

 

PS-3: Operations Fire Prevention

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

PS-4: Water Service

 

PS-4: Water Service

 

 

 

 

 

 

X

 

 

Resulting Level of Significance

 

 

 

 

 

 

LTS

 

Visual Resources

VIS-1: Converter Station Domination of View

 

VIS-1a: Plan Submittal Requirements for Building Materials and Colors

X

X

 

 

X

 

X

 

 

VIS-1b: Plan Submittal Requirements for Landscaping

X

X

 

 

X

 

X

 

 

Resulting Level of Significance

LTS

LTS

 

 

LTS

 

LTS

 

VIS-2: Converter Station Will Create Substantial Light and Glare

 

VIS-2: Plan Submittal Requirements for Lighting

X

X

 

X

X

X

 

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

 

 

VIS-3: Creation of Visual Clutter

 

VIS-3: Landscaping Plan

X

 

 

 

 

 

 

 

 

Resulting Level of Significance

LTS

 

 

 

 

 

 

 

VIS-4: Converter Station Domination of Entrance to Warm Water Cove Park

 

VIS-4a: Landscaping

 

 

 

 

X

 

 

 

 

VIS-4b: Common Fence Design

 

 

 

 

X

 

 

 

 

VIS-4c: Street Lighting along 24th Street

 

 

 

 

X

 

 

 

 

Resulting Level of Significance

 

 

 

 

LTS

 

 

 

VIS-5: Converter Station Domination of View

 

VIS-5a: Street Yard Setback

 

 

 

 

 

X

 

 

 

VIS-5b: Street Yard Landscape

 

 

 

 

 

X

 

 

 

VIS-5c: Architectural Design and Building Colors

 

 

 

 

 

X

 

 

 

Resulting Level of Significance

 

 

 

 

 

RS

 

 

Hazardous Materials and Waste Management

HAZ-1: Removal of Potentially Hazardous Building Materials Resulting from Demolition

 

HAZ-1: Complete an ACM Abatement Plan and an LBP Abatement Plan

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

HAZ-2: Soil Removal

 

HAZ-2: Soil Removal Protocols

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

HAZ-3: Construction-phase Hazardous Materials Use

 

HAZ-3: Reduction of Hazards During Construction Phase

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

HAZ-4: Construction-phase Waste Streams

 

HAZ-4: Management of Construction-phase Waste Streams

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

HAZ-5: Construction-phase Accidental Spills

 

HAZ-5: Construction-phase Spill Prevention, Control, and Countermeasure

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

HAZ-6: Construction-phase Dust and Volatilization of Contaminants

 

HAZ-6: Reduction of Construction Dust and Volatilization of Contaminants

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

HAZ-7: Contaminated Groundwater

 

HAZ-7: Contaminated Groundwater Control

X

 

 

X

X

 

 

 

 

Resulting Level of Significance

LTS

 

 

LTS

LTS

 

 

 

HAZ-8: Operations-phase Hazardous Materials Usage

 

HAZ-8: Control of Operations-phase Hazardous Materials

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

HAZ-9: Operations-phase Waste Streams

 

HAZ-9: Manage Waste Generation, Storage and Disposal During Operations Phase

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

HAZ-10: Operations-phase Accidental Spills

 

HAZ-10: Operations-phase Spill Prevention, Control, and Countermeasure

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

HAZ-11: Operations-phase Fire and Explosion Risk)

 

HAZ-11: Reduction of Fire and Explosion Risk and Emergency Support During Operations Phase

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

HAZ-12: Impacts from Seismic Activity

 

HAZ-12: Manage Seismic Activity

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 

Paleontological Resources

PALEO-1: Disturbance of Fossil Resources

 

PALEO-1: Potential Fossil Resources Protection

X

X

 

X

X

X

X

 

 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

 


1   X = Applicable; Blank = Not Applicable; LTS = Less than Significant; RS = Residual Significant Impact.
2   Note: The impacts and mitigation measures presented in this table reflect mitigating refinements made to the Project between the Draft and Final EIRs.


Return to the Table of Contents. Open the Draft EIR in a new window. On to the next section.