SECTION 6.0 COMPARISON OF ALTERNATIVES

6.1    INTRODUCTION

This section provides a summary comparison of potentially significant impacts for the proposed Project and Project Alternatives, including ancillary facilities. Refer to Section 4.0 (Proposed Project) and Section 5.0 (Project Alternatives) for more information regarding specific impacts and proposed mitigation measures. The No Project Alternative is also included for comparison purposes. Refer to Section A.8.3 in Appendix A for a discussion of alternatives that were considered but eliminated from further consideration, including the rationale for elimination.

The proposed Project and Project Alternatives considered in this comparison of potentially significant impacts are as follows:

6.2    COMPARISON OF ALTERNATIVES

The potentially significant impact findings (including potential impacts, proposed mitigation measures, and residual impact findings) for the proposed and alternative Project components are summarized in Table 6-1.

As shown in Table 6-1, the identified potentially significant impacts, mitigation measures, and residual impact findings for the proposed and alternative converter station sites (including ancillary facilities) in San Francisco and Pittsburg are very similar, except as noted in Section 6.3. The identified potentially significant impacts associated with the submarine cable installation  in the Bay are essentially the same for all converter station sites with the exception of the Pittsburg Standard Oil site as noted in Section 6.3.

6.2.1    San Francisco Converter Stations

6.2.2    Pittsburg Converter Stations

6.2.3    No Project Alternative

As shown in Table 6-1, the No Project Alternative would avoid the potential environmental impacts of the proposed Trans Bay Cable Project, including those associated with the identified Project Alternatives.

The No Project Alternative would involve taking no action to provide additional electrical transmission capacity to San Francisco-i.e., status quo. Under the No Project Alternative, the potential environmental impacts and benefits of the proposed Trans Bay Cable Project would not occur as a direct consequence of Project implementation. However, the No Project Alternative is incapable of meeting the Project goals and objectives, or the CAISO's objectives for solving the near-term and long-term electrical supply and reliability issues in San Francisco and the northern Peninsula area. One potential consequence of the No Project Alternative would be that the relatively inefficient and polluting Mirant Potrero and Hunters Point power plants may need to continue to run in the future to meet San Francisco's electrical supply needs. Another potential consequence of the No Project Alternative would be the lost potential to save an estimated 20 MW of electrical power that is currently expended in line losses, which would be avoided by the proposed Project. In summary, the No Project Alternative does not constitute a reasonable alternative to the proposed HVDC Project.

6.3    ENVIRONMENTALLY SUPERIOR ALTERNATIVE

The No Project Alternative would result in the fewest environmental effects. However, the No Project Alternative would not meet the Project/CAISO goals and is not considered to be a reasonable or feasible alternative. Numerous "non-Project" alternatives were also considered, as discussed in Section A.8.3 in Appendix A of this EIR. None of the various alternatives evaluated are considered to be capable of meeting all of the Project objectives and the related screening criteria for "feasibility" and "environmental impacts avoidance and minimization." Therefore, none of the potential non-Project alternatives were retained for further consideration in this EIR.

The Trans Bay Cable Project Alternatives are considered by the City of Pittsburg to be the only feasible alternative for meeting the Project and CAISO objectives at this point in time.

It is difficult to determine, however, which of Trans Bay Cable Project converter station site alternatives in San Francisco and Pittsburg is the environmentally superior alternative as, with few exceptions, the sites are very similar to each other in terms of potential impacts. The San Francisco Sheedy Converter Station Alternative would avoid the unavoidable adverse significant impact to historic architectural resources associated with the proposed HWC and alternative San Francisco Mirant sites. However, Mirant plans to demolish the buildings considered to be historic (i.e., Station A Complex) on the San Francisco Mirant property due to their deteriorated condition and seismic safety concerns. Locating the proposed Trans Bay Cable Project San Francisco converter station on any one of the three alternative Mirant site layouts would consolidate the electrical station facilities (i.e., PG&E Potrero Substation and the Trans Bay Cable San Francisco converter station) at one location and would avoid potential conflicts with possible future improvements to public access to San Francisco Bay (Impact LU-1). In addition, the required electrical interconnection (115 kV AC) between the Sheedy Converter Station site and the PG&E Potrero Substation is problematic due to potential conflicts with existing underground utilities along Illinois Street. At this stage of the EIR process, no one site in San Francisco is clearly environmentally superior to another.

Of the proposed and alternative converter station sites in Pittsburg (including ancillary facilities), it is also difficult to determine the clearly environmentally superior alternative at this stage of the EIR process. Due to the unavoidable adverse significant noise and visual impacts associated with the Pittsburg West Tenth Street Alternative 2 site, this alternative site is the least preferable from an environmental impact perspective. The Pittsburg West Tenth Street Alternative 1 and Pittsburg Mirant sites both avoid various potentially significant impacts (e.g., potential water quality impacts due to dredging and potential onshore biological impacts associated with installation of AC/DC cables) that would be associated with the proposed Standard Oil Converter Station site. Accordingly, the Pittsburg West Tenth Street Alternative 1 and Pittsburg Mirant alternative sites are considered to be environmentally superior to the proposed Standard Oil Converter Station site and the Pittsburg West Tenth Street Alternative 2 site. At this stage of the EIR process, it is not possible to clearly differentiate the environmentally superior alternative in Pittsburg between the West Tenth Street Alternative 1 site and the Pittsburg Mirant site.


TABLE 6-1
SUMMARY OF POTENTIALLY SIGNIFICANT IMPACTS AND MITIGATION MEASURES


Impact

Mitigation Measure

Proposed San Francisco HWC Converter Station

Proposed Pittsburg Standard Oil Converter Station

Proposed Offshore DC Cable Route

San Francisco Mirant Converter Station Alternative

San Francisco Sheedy Converter Station Alternative

Pittsburg West Tenth Street Converter Station (Alternative 1)

Pittsburg West Tenth Street Converter Station (Alternative 2)

Pittsburg Mirant Converter Station Alternative

No Project Alternative

Air Quality

AIR-1: Fugitive Dust Emissions

                 
 

AIR-1: Fugitive Dust Controls

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

AIR-2: Equipment Exhaust Emissions

                 
 

AIR-2: Exhaust Controls

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

AIR-3: Marine Construction – Criteria Pollutants

                 
 

AIR-3: Marine Vessel Emission Controls

   

X

           
 

Resulting Level of Significance

   

LTS

           

AIR-4: Marine Construction – Toxic Air Contaminants

                 
 

AIR-4: Implement Mitigation Measure AIR-3

   

X

           
 

Resulting Level of Significance

   

LTS

           

Geologic Resources and Soils

GEO-1: Soil Erosion and Compaction

                 
 

GEO-1: Design Project for Erosion Control

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

GEO-2: Asbestos-containing Serpentine

                 
 

GEO-2: Controls for Excavation of Serpentine

X

   

X

X

       
 

Resulting Level of Significance

LTS

   

LTS

LTS

       

GEO-3: Strong Ground Shaking

                 
 

GEO-3: Design to Seismic Design Requirements

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

GEO-4: Liquefaction

                 
 

GEO-4: Design Project for Liquefiable Deposits

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

GEO-5: Shrink-Swell/Subsidence

                 
 

GEO-5: Design Project for Shrink-Swell/Subsidence

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

Water Resources and Quality

WATER-1: Erosion and Contaminated Runoff

                 
 

WATER-1: Erosion Control and Contaminant Source Control

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

WATER-2: Surface Water Quality Impacts from HDD

                 
 

WATER-2: Spill Prevention and Control Plan for HDD

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

WATER-3: Groundwater Quality Impacts from HDD

                 
 

WATER-3: Use of Pilot Hole and Reaming

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

WATER-4: Impacts to Kirker Creek Watershed Drainage Area

                 
 

WATER-4: Kirker Creek Stormwater Management

 

X

             
 

Resulting Level of Significance

 

LTS

             

WATER-5. Water Quality Impacts from Cable Laying Operation

                 
 

WATER-5: Avoidance of Sediment Contamination

   

X

           
 

Resulting Level of Significance

   

LTS

           

WATER-6: Water Quality Impacts from Dredging and Dredge Material Disposal

               
 

WATER-6: Dredging Controls and Sediment Testing Program

   

X

           
 

Resulting Level of Significance

   

LTS

           

WATER-7: Water Quality Impacts from Vessel Fuel Spills

                 
 

WATER-7: Vessel Fuel Spill Response Plan

   

X

           
 

Resulting Level of Significance

   

LTS

           

WATER-8: Flooding

                 
 

WATER-8: Flood Mitigation

         

X

 

X

 
 

Resulting Level of Significance

         

LTS

 

LTS

 

Terrestrial Biological Resources

TBIO-1: Trenching Near Pools Providing Habitat for Special-status Species

                 
 

TBIO-1a: Avoidance and Prevention Measures for Work Near Vernal Pool Habitat

 

X

             
 

TBIO-1b: Awareness Training for Workers

 

X

             
 

TBIO-1c: Biological Monitoring Requirement

 

X

             
 

Resulting Level of Significance

 

LTS

             

TBIO-2: Trenching Near Saltmarsh and Wetland Habitats

                 
 

TBIO-2a: Marking Habitat and Implementing Physical Avoidance Measures

 

X

             
 

TBIO-2b: Monitoring Requirements for Salt Marsh Species

 

X

             
 

TBIO-2c: Awareness Training for Construction Personnel

 

X

             
 

TBIO-2d: Halting Work to Remove Endangered Species from Job Site

 

X

             
 

TBIO-2e: Check Under Parked Vehicles

 

X

             
 

TBIO-2f: Pre-construction Nesting Surveys

 

X

             
 

Resulting Level of Significance

 

LTS

             

TBIO-3: Disturbance or Fill of Wetlands and Streams

                 
 

TBIO-3a : Implement HDD or Comparable Technology Techniques to Avoid Impacts to Kirker Creek and Associated Floodplain Wetlands

 

X

             
 

TBIO-3b: Wetland and Jurisdictional Waters Delineation Survey

 

X

             
 

TBIO-3c: Wetland and Pool Avoidance

 

X

             
 

TBIO-3d: Obtain Streambed Alteration Agreement

 

X

             
 

TBIO-3e : Implement HDD or Comparable Technology Techniques to Avoid Impacts to Wetlands

           

X

   
 

Resulting Level of Significance

 

LTS

       

LTS

   

TBIO-4: Potential Impacts to Giant Garter Snake and Western Pond Turtle

                 
 

TBIO-4a: Avoidance of Habitat and Timing of Construction

 

X

       

X

   
 

TBIO-4b: Worker Training for Giant Garter Snake and Western Pond Turtle

 

X

       

X

   
 

TBIO-4c: Biological Monitoring for Giant Garter Snake and Western Pond Turtle

 

X

       

X

   
 

TBIO-4D: Avoiding Impacts to Wetlands and Habitat

           

X

   
 

Resulting Level of Significance

 

LTS

       

LTS

   

TBIO-5: Potential Impacts to Special-status Raptors and Birds in Construction Laydown Area

             
 

TBIO-5: Pre-construction Nesting Surveys at Construction Laydown Area

 

X

             
 

Resulting Level of Significance

 

LTS

             

TBIO-6: Potential Impacts to Special-status Plants

                 
 

TBIO-6a: Rare Plant Surveys

 

X

             
 

TBIO-6b: Avoidance of Rare Plant Populations

 

X

             
 

Resulting Level of Significance

 

LTS

             

TBIO-7: Potential Impacts to Special-status Plants from Laydown Areas

                 
 

TBIO-7a: Rare Plant Surveys in Laydown Areas

 

X

             
 

TBIO-7b: Avoidance of Special-status Plants

 

X

             
 

Resulting Level of Significance

 

LTS

             

Marine Biological Resources

No potentially significant impacts

                 

Cultural Resources

CUL-1: Disturbance of Archaeological Resources

                 
 

CUL-1a: Archeological Resource Testing

X

   

X

         
 

CUL-1b: Archaeological Resource Data Recovery

X

   

X

         
 

CUL-1c: Archaeological Resource Construction Monitoring

X

   

X

         
 

Resulting Level of Significance

LTS

   

LTS

         

CUL-2: Demolition of Historic Architectural Resources

                 
 

CUL-2a: Recording Architectural Resources

X

   

X

         
 

CUL-2b: Architectural Resource Interpretive Display and/or Interpretive Material

X

   

X

         
 

CUL-2c: Architectural Resource Salvage Opportunities

X

   

X

         
 

Resulting Level of Significance

RS

   

RS

         

CUL-3: Offshore Cable Route Archaeological Resources

                 
 

CUL-3a: Archaeological Resources Geophysical Survey

   

X

           
 

CUL-3b: Archaeological Resources Avoidance

   

X

           
 

CUL-3c: Archaeological Resources Supplemental Underwater Investigation

   

X

           
 

Resulting Level of Significance

   

LTS

           

Land Use and Recreation

LU-1: Potential Conflict with Public Access Improvements

                 
 

LU-1: Public Access

X

     

X

       
 

Resulting Level of Significance

LTS

     

LTS

       

LU-2: Exceedance of Height Allowance

                 
 

LU-2: Height Allowance

 

X

     

X

X

   
 

Resulting Level of Significance

 

LTS

     

LTS

LTS

   

LU-3: Potential Conflict with Kirker Creek Policy

                 
 

LU-3: Kirker Creek Policy

 

X

             
 

Resulting Level of Significance

 

LTS

             

LU-4: Increased Vessel Traffic

                 
 

LU-4a: Vessel Crew Procedures

   

X

           
 

LU-4b: Coast Guard Coordination

   

X

           
 

Resulting Level of Significance

   

LTS

           

LU-5: Potential Conflict with Local Plans and Policies

                 
 

LU-5: Local Plans and Policies Coordination

   

X

           
 

Resulting Level of Significance

   

LTS

           

Commercial Fishing and Marine Transportation

MTRANS-1: Vessel Navigation Hazards

                 
 

MTRANS-1a: Project Registration, Information and Pilotage

   

X

           
 

MTRANS-1b: Compliance with Navigation Rules

   

X

           
 

MTRANS-1c: Precautionary Area

   

X

           
 

Resulting Level of Significance

   

LTS

           

MTRANS-2: Interference with Commercial Fishing Operations

                 
 

MTRANS-2a: Commercial Fishing Avoidance

   

X

           
 

MTRANS-2b: Project Information

   

X

           
 

Resulting Level of Significance

   

LTS

           

MTRANS-3: Interference with Commercial Sport Fishing Operations  

                 
 

MTRANS-3a: Commercial Sport Fishing Avoidance

   

X

           
 

MTRANS-3b: Project Information

   

X

           
 

Resulting Level of Significance

   

LTS

           

Traffic and Transportation

TRAFFIC-1: Cumulative Traffic Impacts

                 
 

TRAFFIC-1: Coordination to Reduce Cumulative Traffic Impacts

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

TRAFFIC-2: Oversized Loads

                 
 

TRAFFIC-2: Coordination of Oversized Loads

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

TRAFFIC-3: Temporary Street Closures Affecting Traffic, Bicycle, and Pedestrian Circulation

             
 

TRAFFIC-3: Signage for Temporary Street Closures

X

   

X

X

       
 

Resulting Level of Significance

LTS

   

LTS

LTS

       

TRAFFIC-4: Impacts on Metro East Light Rail Facility

                 
 

TRAFFIC-4: Reducing Impact on the Movement of MUNI Light Rail Vehicles into and out of the Metro East Maintenance Facility

X

   

X

X

       
 

Resulting Level of Significance

LTS

   

LTS

LTS

       

TRAFFIC-5: Traffic Impacts During Construction

                 
 

TRAFFIC-5: Improve Vehicular Safety

 

X

             
 

Resulting Level of Significance

 

LTS

             

Noise and Vibration

NOISE-1: Converter Station Operations Sound Levels

                 
 

NOISE-1: Noise Barrier Installation for Converter Station

 

X

     

X

X

X

 
 

Resulting Level of Significance

 

LTS

     

LTS

LTS

LTS

 

NOISE-2: Construction Sound Level

                 
 

NOISE-2: Construction Noise Control Measures

           

X

   
 

Resulting Level of Significance

           

RS

   

Public Services and Utilities

PS-1: Construction Fire Hazards

                 
 

PS-1: Construction Fire Prevention

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

PS-2: Existing Onshore Underground Utilities

                 
 

PS-2: Utility Survey

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

PS-3: Operations Fire Hazards

                 
 

PS-3: Operations Fire Prevention

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

PS-4: Water Service

                 
 

PS-4: Water Service

 

X

         

X

 
 

Resulting Level of Significance

 

LTS

         

LTS

 

Visual Resources

VIS-1: Converter Station Domination of View

                 
 

VIS-1a: Plan Submittal Requirements for Building Materials and Colors

X

X

   

X

X

 

X

 
 

VIS-1b: Plan Submittal Requirements for Landscaping

X

X

   

X

X

 

X

 
 

VIS-1C: Landscaping Plan

 

X

             
 

Resulting Level of Significance

LTS

LTS

   

LTS

LTS

 

LTS

 

VIS-2: Converter Station Will Create Substantial Light and Glare

                 
 

VIS-2: Plan Submittal Requirements for Lighting

X

X

 

X

X

X

X

   
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

   

VIS-3: Creation of Visual Clutter

                 
 

VIS-3: Landscaping Plan

X

               
 

Resulting Level of Significance

LTS

               

VIS-4: Converter Station Domination of Entrance to Warm Water Cove Park

                 
 

VIS-4a: Landscaping

       

X

       
 

VIS-4b: Common Fence Design

       

X

       
 

VIS-4c: Street Lighting along 24th Street

       

X

       
 

Resulting Level of Significance

       

LTS

       

VIS-5: Converter Station Domination of View

                 
 

VIS-5a: Street Yard Setback

           

X

   
 

VIS-5b: Street Yard Landscape

           

X

   
 

VIS-5c: Architectural Design and Building Colors

           

X

   
 

Resulting Level of Significance

           

RS

   

Hazardous Materials and Waste Management

HAZ-1: Removal of Potentially Hazardous Building Materials Resulting from Demolition

               
 

HAZ-1: Complete an ACM Abatement Plan and an LBP Abatement Plan

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

HAZ-2: Soil Removal

                 
 

HAZ-2: Soil Removal Protocols

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

HAZ-3: Construction-phase Hazardous Materials Use

                 
 

HAZ-3: Reduction of Hazards During Construction Phase

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

HAZ-4: Construction-phase Waste Streams

                 
 

HAZ-4: Management of Construction-phase Waste Streams

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

HAZ-5: Construction-phase Accidental Spills

                 
 

HAZ-5: Construction-phase Spill Prevention, Control, and Countermeasure

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

HAZ-6: Construction-phase Dust and Volatilization of Contaminants

                 
 

HAZ-6: Reduction of Construction Dust and Volatilization of Contaminants

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

HAZ-7: Contaminated Groundwater

                 
 

HAZ-7: Contaminated Groundwater Control

X

X

 

X

X

       
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

       

HAZ-8: Operations-phase Hazardous Materials Usage

                 
 

HAZ-8: Control of Operations-phase Hazardous Materials

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

HAZ-9: Operations-phase Waste Streams

                 
 

HAZ-9: Manage Waste Generation, Storage and Disposal During Operations Phase

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

HAZ-10: Operations-phase Accidental Spills

                 
 

HAZ-10: Operations-phase Spill Prevention, Control, and Countermeasure

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

HAZ-11: Operations-phase Fire and Explosion Risk)

                 
 

HAZ-11: Reduction of Fire and Explosion Risk and Emergency Support During Operations Phase

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

HAZ-12: Impacts from Seismic Activity

                 
 

HAZ-12: Manage Seismic Activity

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

Paleontological Resources

PALEO-1: Disturbance of Fossil Resources

                 
 

PALEO-1: Potential Fossil Resources Protection

X

X

 

X

X

X

X

X

 
 

Resulting Level of Significance

LTS

LTS

 

LTS

LTS

LTS

LTS

LTS

 

X = Applicable; Blank = Not Applicable; LTS = Less than Significant; RS = Residual Significant Impact.



Return to the Table of Contents. On to the next section.