| SECTION 4.0 | ENVIRONMENTAL SETTING, IMPACTS, AND MITIGATION |
| PROPOSED PROJECT |
4.14 HAZARDOUS MATERIALS AND WASTE MANAGEMENT
This section describes the anticipated hazardous materials to be handled, used, and stored and the hazardous and non-hazardous wastes to be generated, stored, or disposed of in conjunction with the construction and operation of the proposed Trans Bay Cable Project (Project). This section also discusses the procedures and engineering controls to be used to minimize the potential environmental impacts from the onsite handling, storage, and use of these hazardous materials and the generation, handling, and disposal of the hazardous wastes with respect to the onshore converter stations. The sampling and analysis of sediment along the cable route, the routing of the cable to avoid contaminated areas of San Francisco Bay, and the generation and handling of potentially contaminated dredge spoils are addressed in Section 4.4, Water Resources and Quality.
4.14.1 Environmental Setting
4.14.1.1 Site Conditions: San Francisco HWC Converter Station
The proposed San Francisco HWC Converter Station site is located on 23rd Street south of the existing Mirant Potrero Power Plant. The HWC site is currently developed and occupied by several businesses. HWC owns the three buildings on the subject property. Each building has its own street address. The building at 435 23rd Street is occupied by HMR Global Recycling. This building is currently used for recycling electronic equipment such as computers, monitors, servers, and printers. The San Francisco Municipal Railway (MUNI) formerly used the building at 525 23rd Street to store engines and other parts for the MUNI bus fleet. Currently, this building is unoccupied. The proposed converter station would be located on approximately 5.5 acres at the site currently occupied by these two buildings. The proposed use of the HWC site would require the demolition of these existing buildings and facilities before construction of the proposed converter station. The building at 555 23rd Street is occupied by DHL, which uses the facility for incoming and outgoing package delivery services. This building/site is not part of the proposed HWC Converter Station site. Access to this facility was not available when the Phase I site reconnaissance and the Phase I interviews were conducted.
The proposed and alternative AC and DC cable routes associated with the proposed HWC site are shown on Figure A.3-1. The proposed underground direct current (DC) cable route to the HWC site would be installed with horizontal directional drilling (HDD) methods or similar underground drilling methods from an area near the east property line of the HWC
TABLE
4.14-1
SUMMARY OF CONFIRMED AND SUSPECTED SOIL CONTAMINATION ISSUES
AT THE PROPOSED CONVERTER STATION SITES
Locations/ |
Confirmed or Suspected Contaminants |
|||||||||||||
Petroleum Hydrocarbons |
Manufactured Gas Plant PaH Residues |
Metals |
Solvents/ |
Pcbs |
Acm |
Lbp |
RCRA Waste |
Ca Haz Waste |
||||||
TPH-g |
TPH-d |
TPH-mo | ||||||||||||
San Francisco |
||||||||||||||
HWC Site |
Minor |
Heavy |
Heavy |
Likely |
Likely |
Possible |
Possible |
Likely1 |
Likely |
Possible |
Likely |
|||
Pittsburg |
||||||||||||||
Pittsburg Standard Oil Site |
Likely, Minor |
Likely, Minor |
Likely, Minor |
No |
Likely, Minor |
Possible |
Unlikely |
Likely |
Likely |
Unlikely |
Some likely |
|||
Note: Subjective comments on
the possibility of suspected contaminants are based on URS's experience on
similar sites.
1 In addition
to ACM building materials these sites also have confirmed or suspected
naturally occurring serpentine rock containing asbestos.
ACM =
asbestos-containing materials
HWC =
Harrigan Weidenmuller Company
LBP =
lead-based paint
TPH-g =
total petroleum hydrocarbons as gasoline
TPH-d =
total petroleum hydrocarbons as diesel
TPH-mo = total
petroleum hydrocarbons as motor oil
PCB =
polychlorinated biphenyl
VOC =
volatile organic compound
PAH = polynuclear aromatic
hydrocarbon
TABLE 4.14-2
SUMMARY OF CONFIRMED AND POTENTIAL CONTAMINATED GROUNDWATER ISSUES
AT THE PROPOSED CONVERTER STATION SITES
Locations/ |
Confirmed and Potential Groundwater Contamination |
||||||||
Petroleum Hydrocarbons |
Manufactured |
HazMat |
Metals |
Solvents/ |
PCBs |
Cyanide |
|||
TPH-g |
TPH-d |
TPH-mo |
|||||||
San Francisco |
|||||||||
HWC Site |
Minor |
Heavy |
Heavy |
Likely |
Yes, both |
Likely |
Possible |
Unlikely |
Possible |
Pittsburg |
|||||||||
Pittsburg Standard Oil Site |
Likely, Minor |
Likely, Minor |
Likely, Minor |
No |
Unknown |
Likely, Minor |
Possible |
Unlikely |
Unlikely |
Note: Subjective comments on the possibility of suspected
contaminants are based on URS's experience on similar sites.
HWC =
Harrigan Weidenmuller Company
TPH-g =
total petroleum hydrocarbons as gasoline
TPH-d =
total petroleum hydrocarbons as diesel
TPH-mo = total
petroleum hydrocarbons as motor oil
PCB =
polychlorinated biphenyl
VOC =
volatile organic compound
PAH =
polynuclear aromatic hydrocarbon
site to a nearby area in San Francisco Bay to minimize contact with potentially contaminated Bay sediments. Recovered drilling muds and soils would be characterized and disposed of offsite in compliance with applicable regulations.
The proposed underground alternating current (AC) cable route from the HWC site to the Pacific Gas and Electric Company (PG&E) switchyard would start near the middle of the proposed HWC Converter Station site on the north side, cross 23rd Street, run west on the north side of 23rd Street for approximately 450 feet, turn north onto the Mirant Potrero site for approximately 300 feet, turn west into the PG&E substation for approximately 150 feet, and turn north for approximately 100 feet to the connection with the PG&E switchyard. Excavated soils that could not be returned to the cable trench would be characterized and disposed of offsite in compliance with applicable regulations. The detailed Project description is presented in Appendix A of this EIR.
The proposed use of the HWC site would require the demolition of the existing buildings and facilities located at 435 and 525 23rd Street before construction of the proposed converter station. According to the Environmental Data Resources, Inc. (EDR), report prepared for the Phase I Environmental Site Assessment (ESA) for the HWC site (EDR, 2005; URS, 2005a), no sensitive receptors (e.g., schools, hospitals, day-care facilities, or long-term health care facilities) are located within a 0.25-mile radius of the site. The closest park to the HWC site is Warm Water Cove Park, which is located directly south of the site.
According to the Phase I ESA, one of the buildings at the HWC site, the former Airborne Express Building (located at 435 23rd Street, and currently occupied by HMR Recycling), is listed in the Cortese database. The Cortese database identifies public drinking water wells with detectable levels of contamination, hazardous substance sites selected for remedial action, sites with known toxic materials identified through the abandoned site assessment program, sites with underground storage tanks (USTs) that have had a reportable release, and all solid waste disposal facilities that have known migration of contaminants. The Cortese Database provided no details as to why the HWC site was listed. The Phase I ESA identified the following Recognized Environmental Conditions (RECs) for the HWC site:
The groundwater monitoring results for the HWC site have indicated that the elevated concentrations of TPH have not changed significantly since the monitoring began.
The Phase I ESA identified the following REC on surrounding properties:
The DC cable route for the HWC site would come from San Francisco Bay and pass beneath the proposed converter station site. An AC cable would be linked from the proposed HWC Converter Station to the existing switchyard adjacent to the Mirant Potrero site. The proposed AC cable route would exit the HWC site, pass east under 23rd Street, turn north onto the Mirant Potrero site, and proceed to the PG&E substation. The Phase I ESA for the Mirant Potrero site identified the following RECs for the AC cable route:
4.14.1.2 Site Conditions: Pittsburg Standard Oil Converter Station
The proposed Pittsburg Standard Oil Converter Station site is located in a developed area with a mix of industrial and former industrial uses. (This name reflects the site's proximity to the former Standard Oil Avenue; no portion of this site was connected with previous oil processing or storage.) The only structures on the Pittsburg Standard Oil site are two abandoned concrete wastewater storage tanks from the former sanitary wastewater treatment plant located at the site and a small, dilapidated wood-frame building. The remainder of the Pittsburg Standard Oil site was previously occupied by an automobile storage yard but is currently vacant. According to the EDR report (EDR, 2005) that was prepared for the Phase I ESA for the Pittsburg Standard Oil site (URS, 2005c), no sensitive receptors (e.g., schools, hospitals, day-care facilities, or long-term health care facilities) are located within a 0.25-mile radius of the Pittsburg Standard Oil site.
Onshore AC/DC cable routes are proposed between the proposed
Standard Oil Converter Station site and New York Slough as well as an AC cable
on the Mirant Pittsburg property. In addition, offshore submarine cables are
proposed as follows: 1) AC cable between PG&E Pittsburg Substation and
landfall at New York Slough; and 2) DC cable route from New York Slough to
vicinity of Potrero Point in San Francisco. Refer to Section 4.14.1.3 for
information regarding the offshore cable routes. Refer to Figures A.1-1, A.1-3,
and
Map A.2-1 in Appendix A for the locations of these cable routes. The proposed
AC/DC cable route between the Standard Oil Converter Station site and New York
Slough would involve a combination of belowground and aboveground AC, and below
ground AC and DC installation between the site and New York Slough. The
proposed cable route leaves the converter station in a north-northeasterly
direction, cuts diagonally across the former Dow ponds in a northeasterly
direction to the south side of the BNSF railroad track. This portion of the
route would be installed using HDD (or comparable technology). The route then
follows the south side of the railroad ROW within an existing roadway in an
easterly direction to the Delta Diablo Sanitary Sewage plant outfall roadway
(Arcy Lane). At this location, the route then follows the outfall roadway north
to New York Slough (refer to Map A.2-1, Sheet 10 of 10). The portion of the
route between the BNSF railroad tracks and New York Slough would involve
aboveground AC installation and belowground DC installation. Potential
contaminants along the route include solvents, lead, and petroleum
hydrocarbons.
The proposed Standard Oil Converter Station also includes an approximately 0.25-mile-long new access road that would be constructed between the site and the Pittsburg-Antioch Highway. No potential sources of contamination have been identified along this route.
The Phase I ESA identified the following RECs for the Pittsburg Standard Oil site:
The Phase I ESA identified the following surrounding properties as RECs to the Pittsburg Standard Oil site:
The Phase I ESA identified the following RECs related to both of the proposed AC/DC cable routes associated with the Pittsburg Standard Oil site.
4.14.1.3 Site Conditions: Offshore Cable Route
The offshore DC cable route was designed to avoid RWQCB-listed toxic hot spot areas in San Francisco Bay. The concentrations of metals detected in the sediment sampling conducted along the cable route are within typical background levels for the San Francisco Bay Area. Sediment testing along New York Slough shows slightly elevated levels of nickel. Preliminary discussions between the Project proponent and the Dredged Materials Management Office (DMMO) indicated that dredged materials from the New York Slough area could likely be returned to the cable excavation after the cable laying was complete subject to verification sampling.
These issues and the sediment sampling and testing that was conducted along the offshore cable route as well as regional sampling data are described in detail in Section 4.4, Water Resources and Quality.
4.14.2 Regulatory Setting
Table 4.14-3 summarizes the federal, state and regional, and local laws and regulations that apply to the use, storage, transportation, and disposal of hazardous materials at both of the proposed converter station sites. A detailed discussion of the federal, state and regional, and local laws and regulations for hazardous materials is provided in Appendix I.
4.14.3 Environmental Impacts
This section discusses the potential environmental impacts associated with the construction and operation of the proposed San Francisco HWC and Pittsburg Standard Oil converter stations (including ancillary facilities), and the installation of the offshore cables. The San Francisco HWC site has higher levels of known and suspected soil and groundwater contamination than the Pittsburg Standard Oil site. However, the cited potential impacts to human health and the environment from contaminated soil and groundwater are similar for both sites. Consequently, the mitigation measures proposed to reduce the potential impacts to less than significant levels are similar for both sites.
Authority |
Administering Agency |
Requirements and Compliance |
Jurisdiction |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
CERCLA, as amended by SARA; Title III, Emergency Planning and Community Right-to-Know Act (EPCRA) of 1986, 42 USC 11001 et seq.; 40 CFR Parts 302, 355, 370, and 372 |
EPA Region IX; National Response Center; California Office of Emergency Services (OES); San Francisco Department of Public Health Environmental Health Section/ Contra Costa County Health Services Agency |
Project will comply with CERCLA, release notification requirements; SARA Title III, reporting requirements for storing, handling, or producing regulated substances |
Federal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
29 CFR 1910 et seq. 29 CFR 1926 et seq. |
Occupational Safety and Health Administration (OSHA) |
Project will comply with requirements pertaining to employers whose employees handle hazardous materials and extremely hazardous chemicals |
Federal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Clean Air Act Amendments of 1990, Section 112(r), Accidental Release Prevention Program, 42 USC 7412 (r), 40 CFR Part 68 |
EPA Region IX; California OES; San Francisco County/ Contra Costa County |
Project will comply with requirements pertaining to risk management of regulated substances |
Federal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Clean Water Act, Spill Prevention, Control, and Countermeasure Plan, 40 CFR 112 |
EPA Region IX, RWQCB, San Francisco Department of Public Health Environmental Health Section/Contra Costa County Health Services Agency |
Project will comply with requirements designed to prevent the discharge of oil into navigable waters |
Federal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
RCRA, 42 USC 6901 et seq.; 40 CFR 260 et seq.; 49 CFR 172, 173, and 179 |
EPA Region IX, Department of Toxic Substances Control (DTSC) |
Project will comply with RCRA pertaining to a hazardous waste generator identification number to be coordinated through the EPA and the DTSC |
Federal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
California Health & Safety Code, Chapter 6.95, Art. 1 |
San Francisco Department of Public Health Environmental Section/Contra Costa County Health Services Agency |
Project requires facilities handling hazardous materials submit a Hazardous Materials Business Plan (HMBP) to the Certified Uniform Program Agency (CUPA) |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
California Health & Safety Code Section 25270 |
RWQCB |
Project will meet requirements that all above ground petroleum storage tanks must be registered with the State Water Resources Control Board |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
8 CCR 5194 |
San Francisco Department of Public Health Environmental Health Section/Contra Costa County Health Services Agency |
Project will comply with requirements pertaining to employers whose employees are exposed to dusts, fumes, mists, vapors, and gases |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
California Health & Safety Code §§ 25500–25520; 19 CCR §§ 2720–2734 |
San Francisco Department of Public Health Environmental Health Section/Contra Costa County Health Services Agency |
Project will prepare an HMBP |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
California Accidental Release Prevention (CalARP) Program, California Health & Safety Code § 25531 et seq., 19 CCR Division 2, Chapter 4.5 |
California OES, San Francisco Department of Public Health Environmental Section/Contra Costa County Health Services Agency |
Project will meet HMBP requirements and prepare a risk management plan |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
8 CCR § 339, § 3200 et seq., 5139 et seq., 5160 et seq., 5189 et seq. |
California Occupational Safety and Health Administration (Cal-OSHA) |
Project will meet requirements pertaining to the control and management of hazardous substances |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Hazardous Waste Control Act, California Health & Safety Code; 22 CCR 66001 et seq. Chapter 6.5 |
DTSC, San Francisco Department of Public Health Environmental Health Section/Contra Costa County Health Services Agency |
Project will comply with requirements pertaining to the management of hazardous waste |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Health & Safety Code, 22 CCR 67100, Hazardous Waste Source Reduction and Management Review |
DTSC, San Francisco Department of Public Health Environmental Health Section/Contra Costa County Health Services Agency |
Project will comply with the requirements pertaining to waste generators developing a plan for reducing their hazardous wastes |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Health and Safety Code 23CFR 2670 et seq. Underground Storage Tanks |
RWQCB, San Francisco Department of Public Health, Contra Costa County Health Services Agency |
Project will comply with requirements pertaining to underground storage tanks |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
22 CCR 66260-66270 |
DTSC, San Francisco Department of Public Health Environmental Health Section/Contra Costa County Health Services Agency |
Project will comply with requirements pertaining to hazardous waste regulations for generators and transporters of hazardous wastes and owners of hazardous waste Treatment, Storage, and Disposal Facilities (TSDFs) |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Porter-Cologne Water Quality Control Act |
RWQCB |
Project will comply with requirements for the RWQCB to establish reportable quantities of hazardous wastes and hazardous materials based on their potential to degrade the waters of the state |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Uniform Fire Code, Article 80 and others |
City and County of San Francisco/Contra Costa County Fire Protection District (CCCFPD) |
Project will meet provisions regarding fire protection and neutralization systems for hazardous materials |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
State Building Standard Code |
City and County of San Francisco, City of Pittsburg |
Project will meet requirements pertaining to fire prevention, building safety, and other codes |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
California Vehicle Code 32100.5 |
Caltrans |
Project will comply with requirements for transportation materials that may pose an inhalation hazard |
State |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Uniform Building Code |
City and County of San Francisco, City of Pittsburg |
Project will comply with Building Code Requirements |
Local |
CCR =
California Code of Regulations
CERCLA = Comprehensive Environmental
Response, Compensation, and Liability Act of 1980
CFR =
Code of Federal Regulations
EPA =
Environmental Protection Agency
SARA =
Superfund Amendments and Reauthorization Act of 1986
USC =
United States Code
4.14.3.1 Thresholds of Significance
The following thresholds of significance are based on CEQA Guidelines (Appendix G). For the purposes of this EIR, the implementation of the proposed Project would have a significant adverse impact with respect to hazardous materials if it would result in any of the following:
4.14.3.2 San Francisco HWC Converter Station
This section discusses the potential environmental impacts of, and associated mitigation measures for, the proposed San Francisco HWC converter station.
4.14.3.2.1 Construction-related Impacts.
Demolition. The construction of the converter station would require that two existing structures on the site be removed (see Section 4.14.1.1) and that any contamination from asbestos-containing materials (ACMs) and lead-based paint (LBP) be remediated. The extent of the remediation would be based on the results of the ACM and LBP surveys and the subsequent regulatory agency-approved remediation plans. If the potentially hazardous building materials resulting from demolition were not removed and the appropriate remediation was not performed, a significant impact could result.
Impact HAZ-1: Removal of Potentially Hazardous Building Materials Resulting from Demolition. Structures on the converter station site contain or potentially contain ACMs and LBP. Improper removal or remediation of these materials could result in a potentially significant environmental impact.
Mitigation Measure HAZ-1: Complete an ACM Abatement Plan and an LBP Abatement Plan. Complete ACM and LBP investigation and characterization on the converter station site to fill data gaps and to support development of worker safety procedures, in accordance with regulatory requirements to protect construction workers and the public. The ACM and LBP Abatement Plans shall be completed in compliance with application regulations based on the historical and newly acquired ACM and LBP data. If ACM and LBP are confirmed to be present in concentrations above regulatory limits, the Project proponent shall use ACM- and LBP-certified removal contractors and trained asbestos and lead-based paint removal workers, conduct dust monitoring, and properly dispose of generated wastes offsite. The Project proponent shall also prepare a site Health and Safety Plan for this work.
Regulated ACMs (RACMs) are materials with >1.0 percent friable asbestos or material that will become friable during demolition. These materials must be removed before demolition and disposed of off-site as hazardous waste. Non-friable ACMs can be disposed of as non-hazardous waste in a landfill with the appropriate permits.
LBP with total lead content of 1,000 mg/kg and/or leachability of 5.0 mg/L by analysis of the Waste Extraction Test extract analysis would be classified as California hazardous waste, if disposed of separately. Deteriorated paints that meet the hazardous waste criteria must be removed and disposed of separately. If the paint remains firmly affixed to the building material, the building material can be disposed of as non-hazardous building debris. If the demolition disturbs paint containing detectable lead, the work would need to be conducted in accordance with Cal-OSHA's lead in construction regulation (8CCR1532.1).
San Francisco's Exterior Lead Based Paint ordinance (Building Code Section 3407 and Chapter 36 of the Municipal Code) applies to renovation of exterior lead based paint that contains >0.5 percent of lead and to materials painted with lead-based paint. The San Francisco Building Code has a number of requirements including: notification of the San Francisco Building Department 3 days before the work starts, paint removal must take place within a containment or tools equipped with HEPA filters must be used, posting of a multilingual notice when the containment is installed, and notification of the tenants and neighbors of the building 3 days before the work starts.
Implementation Responsibility: Project proponent
Requirements and Timing: Perform surveys and additional testing as needed; conduct required ACM and LBP removal prior to construction; perform dust monitoring for ACM and LBP components during demolition activities.
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-1 would reduce Impact HAZ-1 to a less-than-significant level.
Soil Removal. As discussed in Appendix A, approximately 15,000 cubic yards of soil would need to be excavated and disposed of offsite during the construction of the San Francisco HWC converter station. Non-hazardous soil removed during construction activities, including grading and excavation, at the converter station site would be stockpiled on the site for onsite or offsite reuse or offsite disposal. Were hazardous soils identified in a Phase II investigation and encountered during excavation, they would be loaded directly onto trucks, covered, and hauled for offsite disposal at an appropriate landfill (Class I). Hazardous soil shipments should conducted by licensed hazardous waste transporters using hazardous waste shipping manifests. Excavated soils would be sampled and tested, as necessary, to determine their suitability for reuse. Excavated soil and rock that were not suitable as backfill would be removed from the site and disposed of at an approved landfill. If contaminated soils were not properly sampled, handled, analyzed, or characterized, transported, or disposed of, the soils could present a potentially significant impact.
Impact HAZ-2: Soil Removal. Soils removed during construction of the converter station and cable routes could be contaminated. Improper sampling, handling, analyzing, or characterizing of the soils could result in a potentially significant environmental impact. Soils at the HWC site are likely to be contaminated with metals and either TPH or PAHs, depending on location. In the middle of the site, a naturally occurring subsurface serpentinite ridge may require excavation. Serpentinite contains naturally occurring asbestos and these soils, if disposed of offsite, would likely require disposal as California hazardous waste.
Mitigation Measure HAZ-2: Soil Removal Protocols. Previously uncharacterized soils that are stained or odiferous shall be segregated on plastic, sampled, and characterized for onsite use or offsite disposal. The Soil and Groundwater Management plans (SMP, GMP) shall detail storage, transportation, and disposal options for soil and groundwater excavated/extracted during the converter station construction. They would also specify dust monitoring needs for soil excavation and management.
Previously characterized hazardous soils shall be loaded onto trucks for offsite disposal. Hazardous soil disposal requires that hazardous waste manifests accompany the waste. Hazardous waste transporters shall be required to haul hazardous soils to a Class I hazardous waste landfill. The personnel handling the hazardous soils are required to have met the OSHA hazardous work operations training requirements. A Health and Safety Plan shall be prepared for this work.
Previously characterized non-hazardous soils shall be stockpiled for onsite or offsite reuse or offsite disposal, as needed.
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Implement soil removal and handling procedures as per SMP protocol during construction phase; perform dust monitoring during hazardous soils excavation, as applicable
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-2 would reduce Impact HAZ-2 to a less-than-significant level.
Construction-phase Hazardous Materials Use, Storage, and Disposal. Construction activities would involve truck traffic and heavy equipment operations. During the construction phase, various hazardous materials would be used, including: gasoline, diesel fuel, motor oil, hydraulic fluid, glycol, lubricants, solvents, cleaners, sealers, paints, and paint thinner. The hazardous materials usage that is anticipated to occur at this converter station site during the construction phase is summarized in Table 4.14-4.
Impact HAZ-3: Construction-phase Hazardous Materials Use. Hazardous materials would be used during construction activities. Misuse, inadequate storage, or improper disposal of these materials could result in a potentially significant environmental impact.
Mitigation Measure HAZ-3: Reduction of Hazards During Construction Phase. The hazards presented by the use of hazardous materials during the construction phase are well understood, and the appropriate management controls to mitigate potential impacts shall be implemented. These controls include: 1) developing required management plans, e.g., a Spill Prevention, Control, and Countermeasure Plan (see HAZ-5 for more SPCC Plan details); 2) secondary containment; 3) separate storage of incompatible materials; and 4) proper training of personnel.
Additionally, construction personnel shall be trained in safety and defensive emergency response procedures. Construction personnel shall also receive hazardous-waste-related training that focuses on recognition of potentially contaminated soil and/or groundwater that may be encountered during subsurface excavations for foundations or pipeline/cable trenches. If such contaminated soil or groundwater is suspected, contingency procedures shall be followed to protect worker safety and public health. All vehicles and construction equipment shall be inspected to ensure that no fluids are leaking (e.g., oil, hydraulic fluid, lubricants, or brake fluid) and that all fuels and fluids are stored in proper, clearly labeled containers.
Hazardous materials that must be disposed of will be disposed of as hazardous waste in accordance with the appropriate regulations for storage, transportation, and disposal of hazardous waste.
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Construction contractor to implement hazard reduction measures as detailed above during construction phase
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Material |
Maximum Onsite Quantity |
Use |
Hazards1 |
Storage Type/Area |
Fuels |
||||
Unleaded gasoline |
2,000 gallons |
Fuel for construction equipment |
Acute, chronic, fire |
Equipment service vehicle tanks |
Diesel fuel |
2,000 gallons |
Fuel for construction equipment |
Acute, chronic, fire |
Equipment service vehicle tanks |
Lubricants |
||||
Motor oils |
20–30 gallons |
Lubricating oil for construction equipment and vehicles |
Acute, chronic, fire |
Equipment service vehicle tanks |
Hydraulic oils |
40–50 gallons |
Hydraulic construction equipment |
Acute, chronic, fire |
Equipment service vehicle tanks |
Various greases |
< 25 gallons |
Lubricants for construction equipment and permanent plant equipment including motors, pumps, valves, etc. |
Acute, chronic, fire |
Original shipping containers, equipment service vehicle |
Solvents |
||||
WD-40, similar solvents |
2–3 gallons |
Grease remover |
Acute, chronic, fire |
Original shipping containers, construction warehouse |
Methyl ethyl ketone |
< 25 gallons |
Solvent and cleaner |
Acute, chronic, fire, reactive |
Original shipping containers, construction warehouse |
PVC pipe joint cement |
5–10 gallons |
Solvent based joint cement for assembly of PVC piping |
Acute, chronic, fire |
Original shipping containers, construction warehouse |
PVC pipe cleaner |
10–20 gallons |
Solvent to clean PVC pipe joints prior to completing pipe joint welding (epoxy) |
Acute, chronic, fire |
Original shipping containers, construction warehouse |
Paints |
||||
Paint, miscellaneous |
10–20 gallons |
Paint for touch-up painting of construction equipment and buildings |
Acute, chronic |
Original shipping containers, construction warehouse |
Paint |
400–500 gallons |
Permanent structures paint |
Acute, chronic |
Original shipping containers, construction warehouse |
Paint thinner, miscellaneous |
5–10 gallons |
Thinner for touch-up paint |
Acute, chronic, fire, reactive |
Original shipping containers, construction warehouse |
Paint thinner |
200–300 gallons |
Thinner for structures paint |
Acute, chronic, fire, reactive |
Original shipping containers, construction warehouse |
Aerosol paint |
40–50 12-ounce cans |
Touch-up paint or marking paint |
Acute, chronic, fire, pressure |
Original shipping containers, construction warehouse |
Miscellaneous |
||||
Concrete curing agents |
25–30 gallons |
Curing agent applied to surface of freshly poured concrete to aid in proper curing |
Acute, chronic, fire |
Original shipping containers, construction warehouse |
Concrete form release agents |
25–30 gallons |
Agent sprayed on concrete forms prior to placement of concrete so forms can be stripped after concrete sets |
Acute chronic fire |
Original shipping containers, construction warehouse |
Epoxy Resins |
||||
Epoxy type grout material |
5–10 gallons |
Epoxy based grout material for grouting of equipment |
Fire |
Original shipping containers construction warehouse |
Concrete anchor epoxy |
100–200 epoxy-filled 4–6 ounce glass vials |
Combination epoxy and hardener agents in glass vials used for bonding anchor bolts |
Fire |
Original shipping containers, construction warehouse |
1 Hazard categories are defined by
40 CFR 370.2. Health hazards include acute (immediate) and chronic (delayed).
Physical categories include fire, sudden release of pressure, and reactive.
CFR = Code of Federal Regulations
PVC = polyvinyl chloride
Resulting Level of Significance. Mitigation Measure HAZ-3 would reduce Impact HAZ-3 to a less-than-significant level.
Construction-phase Waste Streams. The following waste streams would be expected to be generated during construction: soils containing hazardous waste and soils that do not contain hazardous waste; ACMs; non-hazardous scrap wood, steel, glass, plastic, and paper; empty hazardous material containers; hazardous solvent waste; hazardous spent lead acid and alkaline batteries; sanitary waste from portable chemical toilets; and non-hazardous storm water runoff. Groundwater collected during construction dewatering is discussed further in Impact and Mitigation Measure HAZ-7 of this section.
Non-hazardous waste would consist of wood refuse, metal and glass containers, and protective plastic equipment coverings. This waste would be generated at an estimated rate of approximately 40 cubic yards per week during construction. Concrete, asphalt, steel, aluminum, and copper from building, foundation, and parking area demolition would be recycled, as practical. The California Integrated Waste Management Board website lists California construction and demolition waste recycling facilities by county. Two facilities that could be used for recycling at the San Francisco HWC Converter Station site are SF Recycling and Disposal, Inc., which is located at 501 Tunnel Avenue, San Francisco, CA, 94134, and Specialty Crushing, Inc., Lot Seawall 352, Pier 94, Cargo and Amador Roads, San Francisco, CA, 94124. Two facilities that could be used for recycling at the Pittsburg Standard Oil Converter Station site are the West Contra Costa Sanitary Landfill at 1 Parr Blvd. Richmond, CA, 94801, and Chip It Recycling at 175 Sandy Lane, Oakley, CA, 94561. Recycling centers vary as to the wastes they accept, so the demolition contractor will make the final arrangements for recycling at specific facilities.
Hazardous wastes would consist of hazardous material containers and minor spill cleanup. Drums, waste oil, and oil filters would be properly managed and recycled. The major source of hazardous waste would likely be contaminated soil.
The total amount of solid waste generated by the construction activities at the San Francisco HWC Converter Station site is expected to be similar to that for normal commercial construction and is not expected to result in significant impacts to public health or to cause adverse effects on local landfill capacity. Information on landfills serving the San Francisco area is presented in Table 4.14-5.
The potential impact associated with the storage and disposal of non-hazardous construction wastes is considered to be potentially significant if the wastes are not managed and disposed of properly.
Impact HAZ-4: Construction-phase Waste Streams. Improper storage and disposal of solid waste and hazardous construction wastes could result in a potentially significant environmental impact.
Mitigation Measure HAZ-4: Management of Construction-phase Waste Streams. The onsite management and offsite disposal procedures of solid wastes (including potentially contaminated soil) shall be in a Solid Waste Management Plan for the Project. Waste shall be stockpiled temporarily before disposal offsite. The local fire department and emergency
TABLE 4.14-5
LANDFILLS SERVING THE SAN FRANCISCO AND PITTSBURG AREAS
Landfill |
Phone Number |
Location |
Class |
Materials Accepted |
Permitted Capacity |
Annual Usage |
Remaining Capacity |
Estimated Closure Date |
Approximate Distance from Sites |
Clean Harbors Buttonwillow Landfill |
(661) 762-7372 |
2500 Lokern Rd, Buttonwillow, CA 93206 |
I |
Solid & Liquid |
13.25 million cubic yards |
352,000 tons |
11,000,000 |
2030 |
260 mi (SF) |
Chemical Waste Management Kettleman Hills Landfill |
(559) 386-9711 |
35251 Old Skyline Rd, Kettleman City, CA 93239 |
I |
Solid & Liquid |
15 million cubic yards |
800,000 cubic yards |
8,000,000 |
2038 |
220 mi (SF) |
Allied Waste Management Keller Canyon Landfill |
(925) 458-9800 |
901 Bailey Rd, Pittsburg, CA 94565 |
II and III |
NA |
3500 tons/day |
821,000 cubic yards |
35,000,000 |
2038 |
40 mi (SF) |
Chemical Waste Management Altamont Landfill |
(800) 449-6349 |
10840 Altamont Pass Rd, Livermore, CA 94550 |
II and III |
Solid & Sludge |
40 million tons |
2 million tons |
14 million tons |
2020 |
50 mi (SF) |
Chemical Waste Management Redwood Landfill Inc. |
(415) 892-2851 |
8950 Redwood Hwy, Novato, CA 94945 |
II and III |
NA |
NA |
NA |
NA |
2038 |
20 mi (SF) |
West Contra Costa Sanitary Landfill |
(510) 233-4330 |
1 Parr Blvd, Richmond, CA 94801 |
II |
NA |
NA |
NA |
NA |
NA |
260 mi (SF) |
Sources: Personal communications
between land fill representatives and URS staff. Turek, 2006; Lewis, 2005;
Atkinson, 2006; Keller Canyon Landfill, 2006.
NA = Not Applicable
management team shall be provided a list of the waste material expected to be generated and stored onsite. Hazardous wastes generated during construction shall be collected in hazardous waste accumulation containers near the point of generation and moved daily to the construction contractor's 90-day hazardous waste storage area at the converter station site. The accumulated waste shall be delivered to an authorized waste management facility.
The exact volume of hazardous wastes to be generated at the San Francisco HWC Converter Station site cannot be estimated at this time, but the estimated amount of excavated soil that would need to be disposed of offsite is estimated at approximately 15,000 cubic yards for this converter station site. Even if this entire amount of excavated soil would need to be disposed of as hazardous waste, it would not exceed a significant portion of the available hazardous waste landfill capacity in California. The capacity details of various landfills for both non-hazardous and hazardous waste are detailed in Table 4.14-5. The capacity and estimates for daily volumes of waste received were verified, as detailed in the personal communications provided in the references for this section.
Management of these wastes shall be the responsibility of the construction contractor(s). Typical management practices required for contractor waste include characterization and recycling when possible, proper storage of waste and debris, including covering daily to prevent wind dispersion, and weekly pickup of waste with disposal of non-hazardous wastes at local Class III landfills.
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Implement waste management procedures during construction phase
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-4 would reduce Impact HAZ-4 to a less-than-significant level.
Construction-phase Accidental Spills. The most likely incident involving hazardous materials during construction would be a small spill or release of fuels, glycol, solvents, paints, or lubricants. A more serious incident could involve a service or refueling vehicle, given the larger volume of fuels normally carried on those types of vehicles. The hazardous materials to be used during the construction phase of the proposed Project are listed in Table 4.14-4. Due to the relatively small quantities of hazardous materials that would be used during construction and the regulatory requirements associated with storage and use of these materials, a spill or an accidental release is the only potentially significant impact.
Impact HAZ-5: Construction-phase Accidental Spills. An accidental spill or a release of hazardous materials could occur during construction. This impact is considered potentially significant.
Mitigation Measure HAZ-5: Construction-phase Spill Prevention, Control, and Countermeasure. The following shall be implemented both to prevent spills from occurring and to minimize impacts in the event that they do occur:
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Establishment and compliance with SPCC and other requirements detailed above performed during construction phase
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-5 would reduce Impact HAZ-5 to a less-than-significant level.
Construction-phase Dust and Volatilization of Contaminants. The potential for environmental and human health effects to occur in conjunction with the generation of hazardous wastes, especially the excavation of contaminated soil and the associated construction dust and volatilization of contaminants, could present a potentially significant impact to worker safety and public health.
Impact HAZ-6: Construction-phase Dust and Volatilization of Contaminants. Excavation of contaminated soil and generation of hazardous waste soils could result in construction dust and volatilization of contaminants that pose environmental and human health risks, particularly to construction workers. This impact is considered potentially significant.
Mitigation Measure HAZ-6: Reduction of Construction Dust and Volatilization of Contaminants. Dust control measures (i.e., keeping the soil wet during excavation) shall be implemented during excavation and construction activities, and dust monitoring shall be performed. Suspected contaminated soil that is stockpiled on the site shall be covered daily with plastic to prevent volatilization of contaminants and to control dust. Contaminated soil may also be loaded directly onto trucks for transport to an appropriate offsite disposal facility. The loaded soils shall be properly covered and manifested as necessary. Dust monitoring shall be performed during excavation and loading of hazardous soils. The accumulated waste will then be delivered to an authorized waste management facility. Dust monitoring shall confirm that the dust control measures are effectively protecting site workers and the public.
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Implement dust control measures during construction phase and conduct dust monitoring
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-6 would reduce Impact HAZ-6 to a less-than-significant level.
Contaminated Groundwater. Groundwater at the San Francisco HWC Converter Station site is known to be contaminated. Upgradient Mirant Potrero site TPH contamination, the history of ASTs and USTs on the HWC site, and the monitoring of HWC site groundwater show or suggest the long-term presence of THP in the groundwater. The presence of a manufactured gas plant (MGP) on the HWC site may indicate that the HWC site is also contaminated with PAHs, and other MGP residues. The site may have metals-contaminated fill which could impact groundwater. Groundwater may be encountered during excavation or other subgrade activities. Potentially significant impacts could occur if this groundwater was not properly handled or contained.
Impact HAZ-7: Contaminated Groundwater. The San Francisco HWC Converter Station site is known to have contaminated groundwater. Groundwater may be encountered during construction and groundwater dewatering. The lead regulatory agency associated with the proposed Project may require control or remediation of the site groundwater for redevelopment of the property. Failure to control the contaminated groundwater flow could result in a potentially significant impact.
Mitigation Measure HAZ-7: Contaminated Groundwater Control. If groundwater was encountered during construction at the converter station site, the water shall be collected onsite in a tank or tanks, sampled, and analyzed. Based on the analytical data, the water shall be characterized for disposal by one of the following methods:
The smaller volume hazardous materials that would be used during the operations phase are typical of those used at other industrial facilities. They would include oils, solvents, and other products (Table 4.14-6). The characteristics of these hazardous materials are described in Table 4.14-7. Use of hazardous materials during the operations phase of the Project could result in a significant impact if not handled properly.
TABLE 4.14-6
HAZARDOUS MATERIALS USED DURING PROJECT
OPERATIONS PHASE
Chemical |
Application |
Storage Location |
Storage or Usage Quantity |
|
Average |
Maximum |
|||
Transformer Oil |
Electric Equipment |
-- |
119,600 gallons initial fill |
Not stored onsite. Initial fill quantity is brought to site at the time of replacement |
Lubricating Oil |
Rotating Equipment |
Throughout plant |
TBD, initial fill |
TBD |
Insulating Oil |
Capacitors |
Throughout plant |
77,400 liters in use, 300 liters in spare capacitors |
Same |
Sulfur Hexaflouride |
Switchgear insulation |
Spares bottles in storage buildings |
550 liters in use, 120 liters spare capacity stored in bottles |
Same |
Diesel Fuel |
Emergency Backup Generator |
-- |
10,000 gallons initial fill |
Maintain full above-ground diesel tank |
TABLE
4.14-7
CHARACTERISTICS OF THE HAZARDOUS MATERIALS USED
DURING PROJECT OPERATIONS AND MAINTENANCE
Material |
CAS Number |
Maximum Onsite Quantity |
Hazards |
Phase |
CalARP Threshold Quantity |
Diesel Fuel in Emergency Generator |
6847-3-6 |
10,000 gallons |
Fire, acute |
Liquid |
NA |
Transformer Oil |
None |
119,000 gallons |
Fire, acute |
Liquid |
NA |
Insulating Oil |
77,700 liters |
Fire, acute |
Liquid |
||
Sulfur Hexaflouride |
670 liters |
Suffocation hazard |
Gas |
CAS = Chemical
Abstract Service
CalARP =
California Accidental Release Prevention
NA = Not
applicable
Impact HAZ-8: Operations-phase Hazardous Materials Usage. Hazardous materials shall be used during operations and maintenance activities. Misuse, inadequate storage, or improper disposal of these materials could result in a potentially significant environmental impact.
Mitigation Measure HAZ-8:
Control of Operations-phase Hazardous Materials. A Hazardous Materials Business Plan (HMBP) shall be developed and
implemented prior to turnover of site management from the construction
contractor to the operating company. All hazardous materials shall be handled
and stored in accordance with applicable codes and regulations. Storage
quantities of all hazardous materials shall be minimized, and non-hazardous
materials shall be substituted for hazardous materials at the converter station
to the extent practicable. Small-quantity chemicals used for maintenance tasks
shall be kept in appropriate inflammable material or corrosive material storage
lockers. Bulk chemicals shall be stored in ASTs, and all other chemicals shall
be stored in their original shipping containers. Incompatible materials shall
be stored in separate storage containment areas. Chemical storage areas and
transfer areas shall be equipped with secondary containment sufficient in size
to contain the volume of the largest container or tank, including an allowance
for rainwater. Areas susceptible to potential leaks and/or spills shall be
paved and bermed or otherwise secondarily contained. Specifically, the
transformers and the diesel ASTs would have secondary containment. Periodic
inspections shall be conducted to ensure that all containers are secure and
properly marked. Piping and tanks will be protected from potential traffic
hazards by concrete or other barriers. Hazardous materials will be delivered to
the converter station periodically. Transportation of these materials shall
comply with all applicable regulations of the U.S. Department of
Transportation, the EPA, DTSC, the California Highway Patrol, and the State
Fire Marshal. An HMBP shall be prepared prior to delivery of specified
hazardous materials to the converter station in conformance with
Title 19 of the California Code of Regulations (CCR) and California Health and
Safety Code Section 25504. The HMBP requires facilities to develop the
following information:
Implementation Responsibility: Project proponent
Requirements and Timing: Implement hazardous materials control measures throughout operations phase of Project
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-8 would reduce Impact HAZ-8 to a less-than-significant level.
Operations-phase Waste Streams. The proposed Project would generate a variety of wastes during operation. These wastes include replaceable parts, rags, and other waste materials and chemicals produced during maintenance activities; equipment fluids; and skimmed oil from an oil/water separator used for rainwater collected in the secondary containment structures. Inert solid waste generated at the converter station during operation would be predominantly maintenance wastes such as scrap metal, wood, and plastic from surplus and deactivated equipment and parts.
Impact HAZ-9: Operations-phase Waste Streams. Improper storage and disposal of operational wastes could result in a potentially significant environmental impact.
Mitigation Measure HAZ-9: Manage Waste Generation, Storage, and Disposal During Operations Phase. Before facility start-up, an application shall be made to DTSC for a hazardous waste generator number. The facility shall not treat, store, or dispose of hazardous waste in a manner that will cause the facility to be characterized as a treatment, storage and disposal facility (TSDF). A detailed waste management plan shall be prepared prior to start-up to ensure proper storage, labeling, packaging, record keeping, manifesting, minimization, and disposal of all hazardous materials and wastes. The waste management plan will include:
Scrap materials such as paper, packing materials, glass, metal, and plastic shall be segregated and managed for recycling. Non-recyclable inert wastes shall be stored in covered trash bins in accordance with local ordinances and picked up by an authorized local trash hauler on a regular basis for transport and disposal in suitable landfill. Skimmed oil collected from equipment drains and other liquids from equipment shall be transported by an authorized carrier to a certified recycling facility.
Implementation Responsibility: Project proponent
Requirements and Timing: Implement waste management procedures throughout operations phase of Project
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-9 would reduce Impact HAZ-9 to a less-than-significant level.
Operations-phase Accidental Spills. The potential for environmental and human health effects associated with the hazardous materials used during the operations phase of the Project is minimal. The most likely incident involving hazardous materials during operation would be a small spill or release of transformer oil or diesel fuel during the refilling of the transformers or the diesel tank for the backup generator.
Impact HAZ-10: Operations-phase Accidental Spills. Non-compliance with regulatory requirements associated with storage, use, and containment of hazardous materials and/or petroleum hydrocarbons could result in accidental spills. The impact from accidental spills of these materials is considered potentially significant.
Mitigation Measure HAZ-10: Operations-phase Spill Prevention, Control, and Countermeasure. The following shall be implemented during operations:
Implementation Responsibility: Project proponent
Requirements and Timing: Implement SPCC measures throughout operations phase of Project
Monitoring Requirements: City of Pittsburg to monitor to ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-10 would reduce Impact HAZ‑10 to a less-than-significant level.
Operations-phase Fire and Explosion Risk. As shown in Tables 4.14-6 and 4.14-7, several materials (e.g., transformer oil and diesel fuel) that would be used and/or stored onsite at the converter station during the operation of the proposed Project are flammable. These materials are considered to pose a greater risk than the other flammable substances because they would be handled in large quantities. The AC and DC cables are not considered to pose a significant fire risk.
Impact HAZ-11: Operations-phase Fire and Explosion Risk. Non-compliance with regulatory requirements associated with storage, use, and containment of flammable materials could result in a fire or explosion. The impact of a fire or explosion is considered potentially significant. If the onsite fire protection equipment could not address the fire, outside agencies would need to be called. This impact is considered potentially significant.
Mitigation Measure HAZ-11: Reduction of Fire and Explosion Risk and Emergency Support During Operations Phase. The flashpoints of transformer oil and diesel fuel are 295°F and 100°F, respectively, and the auto ignition points are 484°F and 494°F, respectively (Sax, 1992; MSDS for transformer oil; MSDS for diesel fuel). The National Fire Prevention Association (NFPA) assigns lubricating oils a fire hazard rating of 1, meaning that the materials "must be preheated before ignition can occur. Materials of these types require considerable preheating, under all ambient temperature conditions, before ignition and combustion can occur" (Siemens, 2006).
The converter station shall have onsite fire protection systems (including emergency backup systems). During the detailed design phase of the proposed Project, potential fire protection designs and systems shall be reviewed with local agencies to finalize design details.
In general, the fire protection system shall consist of automatic detection and firefighting equipment. The fire detection control panel will be located in the control room and will be connected to the control and protection system for remote annunciation. The fire alarm will be initiated automatically by smoke, heat, or flame detectors, or manually by push-button. A combination of detectors will be used, including infrared and ultraviolet detectors, ionization and optical smoke detectors, and rate-of-rise temperature-sensitive detectors, depending on the equipment and/or space being monitored.
Audible alarms and flashing lights will be activated in the event of a fire. The equipment or area where the alarm is triggered will be indicated on the control panel. The firefighting equipment would initiate automatically, using water sprays and curtains or an appropriate gas-extinguishing agent.
Fire detection and automatic firefighting equipment will be connected to a power supply within the fire-detection control panel, which will be connected to the mains via a power supply/battery charger unit with an internal 24-volt battery. A pump house shall be included within the facility with 2 diesel fire-water pumps, each 225 kW. The fire-water pump and backup emergency lighting will be electrically powered by a diesel-powered generator capable of operating at full standby without refueling for 96 hours, as required in a seismically active area.
As an additional mitigation measure, no extra transformer oil will be stored onsite other than what is in the transformers. In case of a fire that exceeded the capacity of the onsite fire control system, the local fire department would respond to control and extinguish the fire. The closest fire stations to the proposed and alternative Converter Station sites are identified in Section 4.12, Public Services and Utilities.
The Project shall use local emergency services in case of emergency. The City and County of San Francisco Fire Department shall be informed of the layout of the converter station and the potential hazards associated with Project operations through the submission of an HMBP. On request, any of the emergency service agencies shall be given MSDSs for the chemicals used at the converter station. These sheets shall be updated as MSDSs are developed or revised, or as more information on these chemicals is made available. Table 4.14-8 identifies government agency and other organizational involvement by type of incident. Table 4.14-9 identifies organizational roles for incidents that involve hazardous materials.
Implementation Responsibility: Project proponent
Requirements and Timing: Implement fire and explosion risk reduction plan during design phase and throughout operations phase
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-11 would reduce Impact HAZ‑11 to a less-than-significant level.
Flooding. The converter station site is not in a floodplain, so no hazardous materials issues related to flooding are considered significant. Therefore, these issues are not addressed further in this section.
Seismic Activity. The converter station site is located in a region known to be associated with fault zones and earthquakes. For detailed information regarding fault zones, see Section 4.3, Geologic Resources and Soils.
Impact HAZ-12: Impacts from Seismic Activity. Failure to abide by the building code for Seismic Zone 4 could lead to damage to the facility and resulting spills of hazardous materials. This impact could be potentially significant.
Mitigation HAZ-12: Manage Seismic Activity. To minimize seismic damage to the facility and the resulting hazardous materials spills, the designers and construction contractor shall follow the Uniform Building Code for Seismic Zone 4. This action would reduce Impact HAZ-12 to a less-than-significant level.
Implementation Responsibility: Project proponent/construction contractor
TABLE
4.14-8
INVOLVEMENT OF GOVERNMENT AGENCIES AND OTHER ORGANIZATIONS BY TYPE OF INCIDENT
Organization |
Emergency Phone # |
Fire |
Spill |
Security |
Medical |
Technical Assistance |
Other |
Contra Costa County Fire Protection District |
911 |
X |
X |
X |
X |
X |
X |
City and County of San Francisco Fire Department |
911 |
X |
X |
X |
X |
X |
X |
Emergency Medical Services |
911 |
X |
X |
X |
|||
Police Department |
911 |
X |
|||||
California Highway Patrol |
911 |
X1 |
|||||
Mt. Diablo Medical Center (Concord) |
911 |
X |
X |
||||
St. Francis Memorial Hospital (San Francisco) |
911 |
X |
X |
||||
Bay Area Air Quality Management District (BAAQMD) |
(415) 771-6000 |
X |
X |
||||
San Francisco Bay Regional Water Quality Control Board |
(510) 226-2300 |
X |
X |
X |
|||
Contra Costa County Hazardous Materials Incident Response Team |
(925) 646-1112 |
X |
X |
||||
San Francisco Hazardous Materials Team |
(415) 335-3700 |
X |
X |
||||
CalEPA; Department of Toxic Substances Control |
(510) 540-2122 |
X |
X |
||||
California Office of Emergency Services |
(800) 852-7550 |
X |
X |
X |
X |
||
California Department of Fish & Game |
(707) 944-5500 |
X2 |
|||||
EPA National Response Center |
(800) 424-8802 |
X2 |
X |
||||
U.S. Department of Transportation |
(510) 286-6444 |
X2 |
X |
||||
U.S. Coast Guard |
(415) 556-2103 |
X2 |
X |
||||
Poison Control Center |
(800) 876-4766 |
X |
X |
X |
|||
PG&E |
(800) 743-5000 |
X |
1 If spill is on highway.
TABLE
4.14-9
ORGANIZATIONAL ROLES FOR INCIDENTS THAT
INVOLVE HAZARDOUS MATERIALS
Agency |
Role |
Fire Department |
Lead agency for all life-safety issues (e.g., fire, explosion, injury or illness, chemical release); assistance in initial care of victims. |
Emergency Medical Services |
Lead agency for medical operations and primary care and transport of victims. |
Police Department |
Lead agency for security-related emergencies (e.g., bomb threat, sabotage, civil disturbance, etc.); maintains order in emergencies involving community evacuations; expedites the movement of vehicles; California Highway Patrol must be notified of violations of hazardous materials transportation regulations or hazardous materials releases onto highways. |
Water District/Sanitation District |
Required to be notified in the event of a discharge of hazardous materials to the sanitary sewer system or storm drain. |
Mt. Diablo Medical Center (Concord) and St. Francis Memorial Hospital (San Francisco) |
Receives and treats injury and illness victims, can provide technical assistance for first aid and basic life support or other issues. |
San Francisco Department of Public Health Environmental Health Section and Contra Costa County Health Services Agency |
Regulates hazardous waste regulations for hazardous waste generators; must be notified of hazardous waste incidents; must be notified of any sanitary concerns (e.g., food poisoning, epidemics, etc.). |
Bay Area Air Quality Management District |
Must be notified of any unauthorized discharges of hazardous materials to the atmosphere. |
Regional Water Quality Control Board – San Francisco Bay Region |
Must be notified of any unauthorized discharges of hazardous materials into the soil, groundwater, or surface water. |
California EPA Department of Toxic Substances Control |
Must be notified of any unauthorized discharges of hazardous materials to the environment; can provide technical assistance for toxicology issues. |
California Office of Emergency Services |
Must be notified of any life threatening releases of hazardous materials into the environment; acts as the lead agency in coordinating responses to large-scale emergencies and regional disasters. Examples of regional incidents the OES would respond to are natural disasters such as floods and earthquakes and civil disasters such as large scale terrorist attacks. The OES would offer support to the EPA, the Coast Guard, and local Fire Departments for large scale environmental disasters. None of these types of incidents are likely to occur at the proposed Project sites. |
California Department of Fish and Game |
Must be notified of any discharges of hazardous materials into surface waters. |
EPA |
Overall regulation of environmental laws; must be notified about discharges of hazardous materials in excess of reportable quantities; must be notified of discharges of oil. |
U.S. Department of Transportation |
Regulates the transportation of hazardous materials on public roads. |
U.S. Coast Guard |
Must be notified of hazardous materials releases into navigable waters. |
Poison Control Center |
Provides information regarding the ingestion or inhalation of poisonous chemicals. |
Requirements and Timing: Comply with building code requirements for Seismic Zone 4 during design, construction, and operation phases
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-12 would reduce Impact HAZ‑12 to a less-than-significant level.
4.14.3.3 Pittsburg Standard Oil Converter Station
This section discusses the potential environmental impacts of, and associated mitigation measures for, the proposed Pittsburg Standard Oil Converter Station.
4.14.3.3.1 Construction-related Impacts.
Demolition. The construction of the converter station would require that the existing structures on the site be removed and that any contamination from ACMs and LBP be remediated. The extent of the remediation would be based on the results of the Phase I ESA and the ACM and LBP surveys and the subsequent regulatory agency-approved remediation plans. If the potentially hazardous building materials were not removed and the appropriate remediation was not performed, a significant impact could result.
Impact HAZ-1: Removal of Potentially Hazardous Building Materials Resulting from Demolition. Existing structures on the converter station site contain or potentially contain ACMs and LBP. Improper removal or remediation of these materials could result in a potentially significant environmental impact.
Mitigation Measure HAZ-1: Complete an ACM Abatement Plan and an LBP Abatement Plan. Phase II ACM and LBP surveys on the converter station site shall be conducted to fill data gaps and to support development of worker safety procedures, in accordance with regulatory requirements to protect construction workers and the public. The ACM and LBP Abatement Plans shall be completed in compliance with applicable regulations based on the historical and newly acquired ACM and LBP data. If ACM and LBP were confirmed to be present in concentrations above regulatory limits, the Project proponent shall use certified asbestos and lead-based paint removal workers, conduct dust monitoring, and dispose of generated wastes offsite. A site Health and Safety Plan shall also be prepared for this work.
RACMs are materials with >1.0 percent friable asbestos or material that would become friable during demolition. These materials must be removed before demolition and disposed of offsite as hazardous waste. Non-friable asbestos containing materials can be disposed of as non-hazardous waste in a landfill with the appropriate permits.
LBP with total lead content of 1,000 mg/kg and/or leachability of 5.0 mg/L by analysis of the Waste Extraction Test extract analysis would be classified as California hazardous waste, if disposed of separately. Deteriorated paints that meet the hazardous waste criteria must be removed and disposed of separately. If the paint remains firmly affixed to the building material, the building material can be disposed of as non-hazardous building debris. If the demolition disturbs paint containing detectable lead, the work would need to be conducted in accordance with Cal-OSHA's lead in construction regulation (8CCR1532.1).
Implementation Responsibility: Project proponent
Requirements and Timing: Perform survey and additional testing as needed and conduct required ACM and LBP removal prior to construction; perform dust monitoring for ACM and LBP components during demolition activities
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-1 would reduce Impact HAZ-1 to a less-than-significant level.
Soil Removal. Approximately 15,000 cubic yards of soil would need to be excavated and disposed of offsite during the construction of the Pittsburg Standard Oil Converter Station. Non-hazardous soil removed during construction activities, including grading and excavation, at the converter station site would be stockpiled on the site for onsite or offsite reuse or offsite disposal. Hazardous soils identified in Phase II investigations or during excavation would be loaded directly onto trucks and covered for offsite disposal at an appropriate (Class I) landfill. Excavated soils would be sampled and tested, as necessary, to determine their suitability for reuse. Excess excavated soil and rock that is not suitable as backfill would be removed from the site and disposed of at an approved landfill. If contaminated soils were not properly sampled, handled, analyzed, or characterized, transported, or disposed of, the soils could present a potentially significant impact.
Impact HAZ-2: Soil Removal. Soils removed during construction of the converter station and cable routes could be contaminated. Improper sampling, handling, analyzing, or characterizing of the soils could result in a potentially significant environmental impact.
Mitigation Measure HAZ-2: Soil Removal Protocols. Previously uncharacterized soils that are stained or odiferous shall be segregated on plastic, sampled, and characterized for onsite use or offsite disposal. The Soil and Groundwater Management Plans shall detail storage, transportation, and disposal options for soil and groundwater excavated/extracted during the converter station construction. The plans shall also specify dust monitoring needs for soil excavation and management.
Previously characterized hazardous soils shall be loaded onto trucks for offsite disposal. Hazardous soil disposal requires that hazardous waste manifests accompany the waste. Hazardous waste transporters shall be required to haul hazardous soils to a hazardous waste landfill that can properly accept them. The personnel handling the hazardous soils are required to have met the OSHA hazardous work operations training requirements. A Health and Safety Plan shall be prepared for this work.
Previously characterized non-hazardous soils shall be stockpiled for onsite or offsite reuse or offsite disposal, as needed.
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Implement soil removal and handling procedures as per SMP during construction phase; perform dust monitoring during hazardous soils excavation, as applicable
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-2 would reduce Impact HAZ-2 to a less-than-significant level.
Construction-phase Hazardous Materials Use, Storage, and Disposal. Construction activities would involve truck traffic and heavy equipment operations. During the construction phase, various hazardous materials would be used including: gasoline, diesel fuel, motor oil, hydraulic fluid, glycol, lubricants, solvents, cleaners, sealers, paints, and paint thinner. The hazardous materials usage that is anticipated to occur at the converter station site during the construction phase is summarized in Table 4.14-4, above.
Impact HAZ-3: Construction-phase Hazardous Materials Use. Hazardous materials would be used during construction activities. Misuse, inadequate storage, or improper disposal of these materials could result in a significant environmental impact.
Mitigation Measure HAZ-3: Reduction
of Hazards During Construction Phase. The
hazards presented by the use of hazardous materials during the construction
phase are well understood, and the appropriate management controls to mitigate
potential impacts shall be implemented. These controls include: 1) developing
required management plans;
2) secondary containment; 3) separate storage of incompatible materials; and 4)
proper training of personnel.
Additionally, construction personnel shall be trained in safety and defensive emergency response procedures. Construction personnel shall also receive hazardous waste-related training that focuses on the recognition of potentially contaminated soil and/or groundwater that may be encountered during subsurface excavations for foundations or pipeline/cable trenches. If such contaminated soil or groundwater is suspected, contingency procedures shall be followed to protect worker safety and public health. All vehicles and construction equipment shall be inspected to ensure that no fluids are leaking (e.g., oil, hydraulic fluid, lubricants, or brake fluid) and that all fuels and fluids are stored in proper, clearly labeled containers.
Hazardous materials that must be disposed of will be disposed of as hazardous waste in accordance with the appropriate regulations for storage, transportation, and disposal of hazardous waste.
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Implement hazard reduction measures described above during construction phase
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-3 would reduce Impact HAZ-3 to a less-than-significant level.
Construction-phase Waste Streams. The following waste streams would be expected to be generated during construction: soil containing hazardous wastes, and soils that do not contain hazardous wastes; ACMs; non-hazardous scrap wood, steel, glass, plastic, and paper; empty hazardous material containers; hazardous solvent waste; hazardous spent lead acid and alkaline batteries; sanitary waste from portable chemical toilets; and non-hazardous storm water runoff. Groundwater collected during construction dewatering is discussed further in Impact and Mitigation Measure HAZ-7 of this section.
Non-hazardous waste would consist of wood refuse, metal and glass containers, and protective plastic equipment coverings. This waste would be generated at an estimated rate of approximately 40 cubic yards per week during construction. Concrete, asphalt, steel, aluminum, and copper from building, foundation, and parking area demolition would be recycled, as practical unless contaminated. The California Integrated Waste Management Board website lists California construction and demolition waste recycling facilities by county. Two facilities that could be used for recycling at the Pittsburg Standard Oil Converter Station are the West Contra Costa Sanitary Landfill at 1 Parr Blvd. Richmond, CA, 94801, and Chip It Recycling at 175 Sandy Lane, Oakley, CA, 94561. Recycling centers vary on the wastes they accept, so the demolition contractor would make the final arrangements for recycling at specific facilities.
Hazardous wastes would consist of hazardous material containers and minor spill cleanup. Drums, waste oil, and oil filters would be properly managed and recycled. The major source of hazardous waste would likely be contaminated soil.
The total amount of solid waste generated by the construction activities at the Pittsburg Standard Oil Converter Station site would be expected to be similar to that for normal commercial construction and would not be expected to result in significant impacts to public health or to cause adverse effects on local landfill capacity. Information on landfills serving the Pittsburg area is presented in Table 4.14-5, above.
The potential impact associated with the storage and disposal of non-hazardous construction wastes is considered to be potentially significant if the wastes are not managed and disposed of properly.
Impact HAZ-4: Construction-phase Waste Streams. Improper storage and disposal of solid waste and hazardous construction wastes could result in a potentially significant environmental impact.
Mitigation Measure HAZ-4: Management of Construction-phase Waste Streams. The onsite management and offsite disposal procedures of solid wastes (including potentially contaminated soil) shall be detailed in a Solid Waste Management Plan for the Project. Waste shall be stockpiled temporarily before disposal offsite. The local fire departments and emergency management teams shall be provided a list of the waste material expected to be generated and stored onsite.
Hazardous wastes generated during construction shall be collected in hazardous waste accumulation containers near the point of generation and moved daily to the construction contractor's 90-day hazardous waste storage area at the converter station site. The accumulated waste shall be delivered to an authorized waste management facility.
The exact volume of hazardous wastes to be generated at the converter station site cannot be estimated at this time, but the estimated amount of excavated soil that would need to be disposed of offsite is estimated at approximately 15,000 cubic yards for this converter station site. Even if this entire amount of excavated soil would need to be disposed of as hazardous waste, it would not exceed a significant portion of the available hazardous waste landfill capacity in California. The capacity details of various landfills for both non-hazardous and hazardous waste are detailed in Table 4.14-5, above. The capacity and estimates for daily volumes of waste received were verified, as detailed in the personal communications provided in the references for this section.
Management of these wastes shall be the responsibility of the construction contractor(s). Typical management practices required for contractor waste include recycling when possible, proper storage of waste and debris, including covering daily to prevent wind dispersion, and weekly pickup of waste with disposal of non-hazardous wastes at local Class III landfills.
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Implement waste management procedures during construction phase
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-4 would reduce Impact HAZ-4 to a less-than-significant level.
Construction-phase Accidental Spills. The most likely incident involving hazardous materials during construction would be a small spill or release of fuels, glycol, solvents paints, or lubricants. A more serious incident could involve a service or refueling vehicle, given the larger volume of fuels normally carried on those types of vehicles. The hazardous materials to be used during the construction phase of the proposed Project are listed in Table 4.14-4, above. Due to the relatively small quantities of hazardous materials that would be used during construction and the regulatory requirements associated with the storage and use of these materials, a spill or an accidental release is the only potentially significant impact.
Impact HAZ-5: Construction-phase Accidental Spills. An accidental spill or a release of hazardous materials could occur during construction. This impact is considered potentially significant.
Mitigation Measure HAZ-5: Construction-phase Spill Prevention, Control, and Countermeasure. The following shall be implemented both to prevent spills from occurring and to minimize impacts in the event that they do occur:
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Establishment and compliance with SPCC and other requirements detailed above performed during construction phase
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-5 would reduce Impact HAZ-5 to a less-than-significant level.
Construction-phase Dust and Volatilization of Contaminants. The potential for environmental and human health effects to occur in conjunction with the generation of hazardous wastes and the associated construction dust and volatilization of contaminants, could present a potentially significant impact to worker safety and public health.
Impact HAZ-6: Construction-phase Dust and Volatilization of Contaminants. Excavation of contaminated soil and the generation of hazardous waste soils could result in construction dust and volatilization of contaminants that pose environmental and human health risks, particularly to construction workers. This impact is considered potentially significant.
Mitigation Measure HAZ-6: Reduction of Construction Dust and Volatilization of Contaminants. Dust control measures (i.e., keeping the soil wet during excavation) shall be implemented during excavation and construction activities, and dust monitoring shall be performed. Suspected contaminated soil that is stockpiled on the sites shall be covered daily with plastic to prevent volatilization of contaminants and to control dust. Contaminated soil may also be loaded directly onto trucks for transport to an appropriate offsite disposal facility. The loaded soils shall be properly covered and manifested as necessary. Dust monitoring shall be performed during excavation and loading of hazardous soils. The accumulated waste shall then be delivered to an authorized waste management facility. Dust monitoring shall confirm that the dust control measures are effectively protecting site workers and the public.
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Implement dust control measures during construction phase and conduct dust monitoring
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-6 would reduce Impact HAZ-6 to a less-than-significant level.
Contaminated Groundwater. Groundwater at the converter station site could be contaminated. Potentially significant impacts could occur if this groundwater is not properly handled or contained.
Impact HAZ-7: Contaminated Groundwater. The converter station site may have contaminated groundwater. This groundwater may be encountered during excavation, construction dewatering, or other subgrade activities. Control or remediation of the site groundwater may be a requirement for redevelopment of the property by the lead regulatory agency for the proposed Project. Failure to properly treat and/or dispose of water collected during dewatering activities or to control the contaminated groundwater flow could result in a potentially significant impact to the site or to downgradient sites and/or water bodies.
Mitigation Measure HAZ-7: Contaminated Groundwater Control. If groundwater is encountered during construction at the converter station site, the water shall be collected onsite in a tank or tanks, sampled, and analyzed. Based on the analytical data, the water shall be characterized for disposal by one of the following methods:
If groundwater was encountered at the Pittsburg Standard Oil Converter Station site and it was found to be contaminated, it is possible that the Regional Water Quality Control Board would require groundwater control as part of the development plan for the Project on the site. Contamination at the Pittsburg Standard Oil site, if any, would likely be caused by offsite sources which would probably not require onsite remedial action. Potential groundwater-remedial strategies would depend on a number of factors including: site contaminants, evaluation of impacts to human health and the environment, and evaluation of the technical merits of available remedial strategies. Based on these factors the final selection would be negotiated between the RWQCB and TBC. Potential remedial options provided herein are for informational purposes only. Potential groundwater control methodologies include installing a slurry wall around a portion or the entire contaminated site combined with groundwater pump and treatment and discharge of treated groundwater to a storm drain/sewer system under the authority of an NPDES permit. Other alternative technologies include in-situ biological treatment and in-situ oxidation or reduction, depending on the site-specific contaminants and hydrogeological conditions.
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Implement groundwater control measures during construction (and continue into operational phase, if necessary), and perform groundwater collection, storage, treatment, and discharge monitoring, as necessary
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-7 would reduce Impact HAZ-7 to a less-than-significant level.
4.14.3.3.2 Operations-related Impacts.
Operations-phase Hazardous Materials Usage. The proposed converter station is designed to minimize the use of hazardous materials. Storage facilities and handling equipment for hazardous materials have been designed so that in the unlikely event of an accidental release of a hazardous material, the potential impact would be kept below designated thresholds of significance.
After the construction of the proposed Project, transformer oil for the electric equipment and diesel fuel for the emergency backup generator and fire pumps would be the only large volume hazardous materials present at the converter station (other than incidental painting and janitorial supplies). The initial fill of transformer oil would be 119,600 gallons for four transformers, one of which would serve as an emergency backup. The transformer oil at the converter station would not be stored on the site before the transformers were filled; the initial fill quantities would be brought to the site when the transformers were ready to be filled.
The initial fill of diesel fuel for the backup generator at the converter station would be 10,000 gallons, based on a 900-kilowatt (kW) emergency diesel generator and two fire water pumps that are capable of operating for 96 hours at full standby without refueling. The aboveground diesel tank for the converter station would be kept full during operation of the converter station.
The potential public health impacts associated with the operation of the converter station would be mitigated by the use of containment structures and the development and implementation of Emergency Response Plans, an SPCC Plan, safety programs, and employee training. Design features of the proposed Project that would reduce potential impacts to below the level of significance include the following:
The small quantity hazardous materials that would be used during the operations and maintenance phase are typical of those used at other industrial facilities. They would include oils, solvents, and other products (see Table 4.14-6, above). The characteristics of these hazardous materials are described in Table 4.14-7, above. Use of hazardous materials during the operations and maintenance phase of the Project could result in a potentially significant impact if not handled properly.
Impact HAZ-8: Operations-phase Hazardous Materials Usage. Hazardous materials shall be used during operations and maintenance activities. Misuse, inadequate storage, or improper disposal of these materials could result in a potentially significant environmental impact.
Mitigation Measure HAZ-8: Control of Operations-phase Hazardous Materials. A Hazardous Materials Business Plan (HMBP) shall be developed and implemented prior to turnover of site management from the construction contractor to the operating company. All hazardous materials shall be handled and stored in accordance with applicable codes and regulations. Storage quantities of all hazardous materials shall be minimized, and non-hazardous materials shall be substituted for hazardous materials at the converter station to the extent practicable. Small-quantity chemicals used for maintenance tasks shall be kept in appropriate inflammable material or corrosive material storage lockers. Bulk chemicals shall be stored in ASTs, and all other chemicals shall be stored in their original shipping containers. Incompatible materials shall be stored in separate storage containment areas. Chemical storage areas and transfer areas shall be equipped with secondary containment sufficient in size to contain the volume of the largest container or tank, including an allowance for rainwater. Areas susceptible to potential leaks and/or spills shall be paved and bermed or otherwise secondarily contained. Specifically, the transformers and the diesel ASTs would have secondary containment. Periodic inspections shall be conducted to ensure that all containers are secure and properly marked. Piping and tanks will be protected from potential traffic hazards by concrete or other barriers. Hazardous materials will be delivered to the converter station periodically. Transportation of these materials shall comply with all applicable regulations of the U.S. Department of Transportation, the EPA, DTSC, the California Highway Patrol, and the State Fire Marshal. An HMBP shall be prepared prior to delivery of specified hazardous materials to the converter station in conformance with Title 19 of the California Code of Regulations (CCR) and California Health and Safety Code Section 25504. The HMBP requires facilities to develop the following information:
Implementation Responsibility: Project proponent
Requirements and Timing: Implement hazardous materials control measures throughout operations phase of Project
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-8 would reduce Impact HAZ-8 to a less-than-significant level.
Operations-phase Waste Streams. The proposed Project would generate a variety of wastes during operation. These wastes include replaceable parts, rags, and other waste materials and chemicals produced during maintenance activities; equipment fluids; and skimmed oil from an oil/water separator used for rainwater collected in the secondary containment structures. Inert solid waste generated at the converter station during operation would be predominantly maintenance wastes such as scrap metal, wood, and plastic from surplus and deactivated equipment and parts.
Impact HAZ-9: Operations-phase Waste Streams. Improper storage and disposal of operational wastes could result in a significant environmental impact. This impact is considered potentially significant.
Mitigation Measure HAZ-9: Manage Waste Generation, Storage, and Disposal During Operations Phase. Before facility start-up, an application shall be made to DTSC for a hazardous waste generator number. The facility shall not treat, store, or dispose of hazardous waste in a manner that will cause the facility to be characterized as a treatment, storage and disposal facility (TSDF). A detailed waste management plan shall be prepared prior to start-up to ensure proper storage, labeling, packaging, record keeping, manifesting, minimization, and disposal of all hazardous materials and wastes. The waste management plan will include:
Scrap materials such as paper, packing materials, glass, metal, and plastic shall be segregated and managed for recycling. Non-recyclable inert wastes shall be stored in covered trash bins in accordance with local ordinances and picked up by an authorized local trash hauler on a regular basis for transport and disposal in suitable landfill. Skimmed oil collected from equipment drains and other liquids from equipment shall be transported by an authorized carrier to a certified recycling facility.
Implementation Responsibility: Project proponent
Requirements and Timing: Implement waste management procedures throughout operations phase of Project
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-9 would reduce Impact HAZ-9 to a less-than-significant level.
Operations-phase Accidental Spills. The potential for environmental and human health effects associated with the hazardous materials used during the operations phase of the Project is minimal. The most likely incident involving hazardous materials during operation and maintenance would be a small spill or release of transformer oil or diesel fuel during the refilling of the transformers or the diesel tank for the backup generator.
Impact HAZ-10: Operations-phase Accidental Spills. Non-compliance with regulatory requirements associated with storage, use, and containment of hazardous materials and/or petroleum hydrocarbons could result in accidental spills. The impact from accidental spills of these materials is considered potentially significant.
Mitigation Measure HAZ-10: Operations-phase Spill Prevention, Control, and Countermeasure. The following shall be implemented during operations:
Implementation Responsibility: Project proponent
Requirements and Timing: Implement SPCC measures throughout operations phase of Project
Monitoring Requirements: City of Pittsburg to monitor to ensure compliance
Resulting Level of
Significance. Mitigation Measure HAZ-10
would reduce Impact
HAZ-10 to a less-than-significant level.
Operations-phase Fire and Explosion Risk. As shown in Tables 4.14-6 and 4.14-7, above, several materials (i.e., transformer oil and diesel fuel) that would be used and/or stored onsite at the converter station during the operation of the proposed Project are flammable. These materials are considered to pose a greater risk than the other flammable substances because they would be handled in large quantities. An overheated AC or DC cable is not considered to be a significant fire risk by the project engineers.
Impact HAZ-11: Operations-phase Fire and Explosion Risk. Non-compliance with regulatory requirements associated with storage, use, and containment of flammable materials could result in a fire or explosion. If the onsite fire protection equipment could not address the fire, outside agencies would need to be called. This impact is considered potentially significant. The impact of a fire or explosion is considered potentially significant.
Mitigation Measure HAZ-11: Reduction of Fire and Explosion Risk and Emergency Support During Operations Phase. The flashpoints of transformer oil and diesel fuel are 295°F and 100°F, respectively, and the auto ignition points are 484°F and 494°F, respectively (Sax, 1992; MSDS for transformer oil; MSDS for diesel fuel). The National Fire Prevention Association (NFPA) assigns lubricating oils a fire hazard rating of 1, meaning that the materials "must be preheated before ignition can occur. Materials of these types require considerable preheating, under all ambient temperature conditions, before ignition and combustion can occur" (Siemens, 2006).
The converter station shall have onsite fire protection systems (including emergency backup systems). During the detailed design phase of the proposed Project, potential fire protection designs and systems shall be reviewed with local agencies to finalize design details.
In general, the fire protection system shall consist of automatic detection and firefighting equipment. The fire detection control panel shall be located in the control room and shall be connected to the control and protection system for remote annunciation. The fire alarm shall be initiated automatically by smoke, heat, or flame detectors; or manually by push-button. A combination of detectors shall be used, including infrared and ultraviolet detectors, ionization and optical smoke detectors, and rate-of-rise temperature-sensitive detectors, depending on the equipment and/or space being monitored.
Audible alarms and flashing lights shall be activated in the event of a fire. The equipment or area where the alarm is triggered shall be indicated on the control panel. The firefighting equipment would initiate automatically, using water sprays and curtains or an appropriate gas-extinguishing agent.
Fire detection and automatic firefighting equipment shall be connected to a power supply within the fire-detection control panel, which will be connected to the mains via a power supply/battery charger unit with an internal 24-volt battery. A pump house shall be included within the facility with 2 diesel fire-water pumps, each 225 kW. The fire-water pump and backup emergency lighting shall be electrically powered by a diesel-powered generator capable of operating at full standby without refueling for 96 hours, as required in a seismically active area.
As an additional mitigation measure, no extra transformer oil shall be stored onsite other than what is in the transformers. In case of a fire that exceeded the capacity of the onsite fire control system, the local fire department would respond to control and extinguish the fire. The closest fire stations to the proposed and alternative converter station sites are identified in Section 4.12, Public Services and Utilities.
The Project shall use local emergency services in case of emergency. The Contra Costa Fire Protection District shall be informed of the layout of the converter station and the potential hazards associated with Project operations through the submission of an HMBP. On request, any of the emergency service agencies shall be given MSDSs for the chemicals used at the converter station. These sheets shall be updated as MSDSs are developed or revised, or as more information on these chemicals is made available. Table 4.14-8 identifies government agency and other organizational involvement by type of incident. Table 4.14-9 identifies organizational roles for incidents that involve hazardous materials.
Implementation Responsibility: Project proponent
Requirements and Timing: Implement fire and explosion risk reduction plan during design phase and throughout operations phase
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of Significance. Mitigation Measure HAZ-11 would reduce Impact HAZ-11 to a less-than-significant level.
Flooding. The Pittsburg Standard Oil Converter Station site is not in a floodplain, so no hazardous materials issues related to flooding are considered significant. Therefore, these issues are not addressed further in this section.
Seismic Activity. The converter station site is located in a region known to be associated with fault zones and earthquakes. For detailed information regarding fault zones, see Section 4.3, Geologic Resources and Soils.
Impact HAZ-12: Impacts from Seismic Activity. Failure to abide by the building code for Seismic Zone 4 could lead to damage to the facilities and resulting spills of hazardous materials. This impact could be potentially significant.
Mitigation HAZ-12: Manage Seismic Activity. To minimize seismic damage to the facilities with resulting hazardous materials spills, the designers and construction contractor shall follow the Uniform Building Code for Seismic Zone 4. This action would reduce Impact HAZ-12 to a less-than-significant level.
Implementation Responsibility: Project proponent/construction contractor
Requirements and Timing: Comply with building code requirements for Seismic Zone 4 during design, construction, and operations phases
Monitoring Requirements: City of Pittsburg to monitor and ensure compliance
Resulting Level of
Significance. Mitigation Measure HAZ-12
would reduce Impact
HAZ-12 to a less-than-significant level.
4.14.3.4 Offshore Cable Route
4.14.3.4.1 Construction-related Impacts. Offshore cable route construction impacts, including dredging, are addressed in Section 4.4, Water Resources and Quality.
4.14.3.4.2 Operations-related Impacts. Offshore cable route operations-related impacts are addressed in Section 4.4, Water Resources and Quality.
Atkinson, M. 2006. Personal communication between Mark Atkinson, Clean Harbors, Buttonwillow Landfill, and Renee McFarlan, URS Corporation, February.
Blymyer Engineers, Inc. 1990. Environmental Site Assessment, John Shirley, 435, 525, and 555 23rd Street, San Francisco, California. September 13.
EDR. 2005. Environmental Data Resources Report No. 01415342.2r, 525 23rd Street Report. May.
Keller Canyon Landfill. 2006.
Website accessed at: www.alliedwasteservicesofcontracosta
county.com.
Lewis, K. 2005. Personal communication between Ken Lewis, Chemical Waste Management, Altamont Landfill, and Renee McFarlan, URS Corporation, November.
Sax. 1992. Sax's Dangerous Properties of Industrial Materials. Eighth Edition. Edited by Richard J. Lewis, Sr. New York: Van Nostrand Reinhold, July.
Siemens. 2006. Written communication from Siemens (Lindsay Martin), January.
Turek, P. 2006. Personal communication between Paul Turek, Chemical Waste Management, Kettleman Hills Landfill, and Renee McFarlan, URS Corporation. January.
URS. 2005a. Phase I Environmental Site Assessment, Proposed Converter Station Site at the Harrigan Weidenmuller Company Property at 435, 525, and 555 Twenty-Third Street, San Francisco, California.
2005b. Phase I Environmental Site Assessment, Mirant Potrero Converter Station Site at 1201 Illinois Street, San Francisco, California.
2005c. Phase I Environmental Site Assessment, Standard Oil Site at 1301 Standard Oil Avenue, Pittsburg, California.
2005d. Phase I Environmental Site Assessment, Proposed West Tenth Street Converter Station Site at 610, 620, 630, 640, and 650 West Tenth Street, Pittsburg, California.
2005e. Phase I Environmental Site Assessment, Mirant Pittsburg Power Plant Property at 696 West 10th Street and Pacific Gas and Electric Company Substation at 696-B West 10th Street, Pittsburg, California.
2006a. Phase I Environmental Site Assessment, Sheedy Drayage Property at 1215 to 1275 Michigan Street, San Francisco, California.
2006b. Phase II Soil and Groundwater Investigation Report for Property at 564-650 West 10th Street, Pittsburg, California.
| Return to the Table of Contents. | On to the next section. |